SCHEDULES

SCHEDULE 9 Review of old mineral planning permissions

Permissions ceasing to have effect

12

(1)

Subject to paragraph 8(11), where no application under paragraph 9 in respect of an active Phase I or II site has been served on the planning authority by the date specified in the first or, as the case may be, the second list as the date by which applications under that paragraph in respect of that site are to be made, or by such later date as may at any time be agreed upon in writing between the applicant and the authority, each relevant planning permission relating to the site shall cease to have effect, except in so far as it imposes any restoration or aftercare condition, on the day following the last date on which such an application may be made.

(2)

The reference in sub-paragraph (1) to the date specified in the first or, as the case may be, the second list as the date by which applications under paragraph 9 are to be made in respect of any Phase I or II site is a reference to the date specified for that purpose in respect of that site in that list as prepared by the planning authority or, where that date has been varied by virtue of any provision of this Schedule, to that date as so varied.

(3)

Subject to sub-paragraph (4), no relevant planning permission which relates to a dormant site shall have effect to authorise the carrying out of minerals development unless—

(a)

an application has been made under paragraph 9 in respect of that site, and

(b)

that permission has effect in accordance with paragraph 9(5).

(4)

A relevant planning permission which relates to a Phase I or II site not included in the first list shall cease to have effect, except in so far as it imposes any restoration or aftercare condition, on the day following the last date on which an application under sub-paragraph (1) of paragraph 6 may be made in respect of that site unless an application has been made under that sub-paragraph by that date in which event, unless the site is added to that list, such a permission shall cease to have effect when the following conditions are met—

(a)

the proceedings on that application, including any proceedings on or in consequence of the application under section 239, have been determined, and

(b)

any time for appealing under paragraph 6(11) or (12), or applying or further applying under paragraph 6(1), (where there is a right to do so) has expired.