Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
9(1)Any person who is the owner of any land, or who is entitled to an interest in a mineral, may, if that land or mineral is or forms part of a dormant site or an active Phase I or II site, apply to the planning authority to determine the conditions to which the relevant planning permissions relating to that site are to be subject.S
(2)An application under this paragraph shall be in writing and shall—
(a)identify the mineral site to which the application relates,
(b)specify the land or minerals comprised in the site of which the applicant is the owner or, as the case may be, in which the applicant is entitled to an interest,
(c)identify any relevant planning permissions relating to the site,
(d)identify, and give an address for, each other person that the applicant knows or, after reasonable inquiry, has cause to believe to be an owner of any land, or entitled to any interest in any mineral, comprised in the site,
(e)set out the conditions to which the applicant proposes the permissions referred to in paragraph (c) should be subject, and
(f)be accompanied by the appropriate certificate.
(3)For the purposes of sub-paragraph (2), the appropriate certificate is each of the certificates which would be required, under or by virtue of sections 34 and 35, to accompany the application if it were an application for planning permission for minerals development, but with such modifications as are required for the purposes of this paragraph; and sections 34(3) and (4) and 35(5) shall have effect in relation to any certificate purporting to be the appropriate certificate.
(4)Section 35 shall have effect, with any necessary modifications, as if subsection (1) also authorised a development order to provide for publicising applications under this paragraph.
(5)Where the planning authority receive an application under this paragraph in relation to a dormant site or an active Phase I or II site they shall determine the conditions to which each relevant planning permission relating to the site is to be subject; and any such permission shall, from the date when the conditions to which it is to be subject are finally determined, have effect subject to the conditions which are determined under this Schedule as being the conditions to which it is to be subject.
(6)The conditions imposed by virtue of a determination under sub-paragraph (5)—
(a)may include any conditions which may be imposed on a grant of planning permission for minerals development;
(b)may be in addition to, or in substitution for, any existing conditions to which the permission in question is subject.
(7)In determining that a relevant planning permission is to be subject to any condition relating to development for which planning permission is granted by a development order, the planning authority shall have regard to any guidance issued for the purpose by the Secretary of State.
(8)Subject to sub-paragraph (9), where, within the period of three months from the planning authority having received an application under this paragraph, or within such extended period as may at any time be agreed upon in writing between the applicant and the authority, the authority have not given notice to the applicant of their decision upon the application, the authority shall be treated as having at the end of that period or, as the case may be, that extended period, determined that the conditions to which any relevant planning permission to which the application relates is to be subject are those specified in the application as being proposed in relation to that permission; and any such permission shall, from that time, have effect subject to those conditions.
(9)Where a planning authority, having received an application under this paragraph, are of the opinion that they are unable to determine the application unless further details are supplied to them, they shall within the period of one month from having received the application give notice to the applicant—
(a)stating that they are of such opinion, and
(b)specifying the further details which they require,
and where the authority so serve such a notice the period of three months referred to in sub-paragraph (8) shall run not from the authority having received the application but from the time when the authority have received all the further details specified in the notice.
(10)Without prejudice to the generality of sub-paragraph (9), the further details which may be specified in a notice under that sub-paragraph include any—
(a)information, plans or drawings, or
(b)evidence verifying any particulars of details supplied to the authority in respect of the application in question,
which it is reasonable for the authority to request for the purpose of enabling them to determine the application.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: