Town and Country Planning (Scotland) Act 1997, Section 124 is up to date with all changes known to be in force on or before 28 February 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

124 Time limits.S

(1)Where there has been a breach of planning control consisting in the carrying out without planning permission of building, engineering, mining or other operations in, on, over or under land, no enforcement action may be taken after the end of the period of 4 years beginning with the date on which the operations were substantially completed.

(2)Where there has been a breach of planning control consisting in the change of use of any building to use as a single dwellinghouse, no enforcement action may be taken after the end of the period of 4 years beginning with the date of the breach.

(3)In the case of any other breach of planning control, no enforcement action may be taken after the end of the period of 10 years beginning with the date of the breach.

(4)Subsections (1) to (3) do not prevent—

(a)the service of a breach of condition notice in respect of any breach of planning control if an enforcement notice in respect of the breach is in effect, or

(b)taking further enforcement action in respect of any breach of planning control if, during the period of 4 years ending with that action being taken, the planning authority have taken or purported to take enforcement action in respect of that breach.

Modifications etc. (not altering text)

Back to top

Options/Help

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?