Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997, Cross Heading: Grant of consent subject to conditions is up to date with all changes known to be in force on or before 08 January 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Without prejudice to the generality of section 14(1), the conditions subject to which listed building consent may be granted may include conditions with respect to—
(a)the preservation of particular features of the building, either as part of it or after severance from it;
(b)the making good, after the works are completed, of any damage caused to the building by the works;
(c)the reconstruction of the building or any part of it following the execution of any works, with the use of original materials so far as practicable and with such alterations of the interior of the building as may be specified in the conditions.
(2)Listed building consent may also be granted subject to a condition reserving specified details of the works (whether or not set out in the application) for subsequent approval by the planning authority or, in the case of consent granted by the Secretary of State, specifying whether the reserved details are to be approved by the planning authority or by him.
(3)In granting a listed building consent a planning authority may attach to the consent a condition that no demolition of the listed building shall take place until either or both of the following requirements have been met—
(a)[F1a planning obligation under section 75 of the principal Act] for the regulation of the development of the site of the listed building in accordance with a current planning permission has been [F2entered into and the relevant instrument by which that obligation is entered into has been recorded in the Register of Sasines or, as the case may be, registered in the Land Register of Scotland under that section] ;
(b)the planning authority are satisfied that contracts have been placed either—
(i)for the redevelopment of the site, or
(ii)for its conversion to an acceptable open space,
in accordance with a current planning permission.
Textual Amendments
F1Words in s. 15(3)(a) substituted (3.8.2009) by The Planning etc. (Scotland) Act 2006 (Consequential Amendments) Order 2009 (S.S.I. 2009/256), arts. 1(3), 3(2)(a)
F2Words in s. 15(3)(a) substituted (3.8.2009) by The Planning etc. (Scotland) Act 2006 (Consequential Amendments) Order 2009 (S.S.I. 2009/256), arts. 1(3), 3(2)(b)
(1)[F3Any listed building consent shall be granted subject to a condition that works permitted by that consent shall be commenced within such period as the planning authority may specify in the consent.]
[F3A listed building consent lapses—
(a)on the expiration of such period (beginning with the date on which the consent is granted) as the planning authority may, for the purposes of this section, specify in the consent, or
(b)if no period is so specified, on the expiration of a period of 3 years (beginning with that date),
unless the works permitted by the consent are begun before that expiration.
(1A)Subsection (1) does not apply to a listed building consent granted before the date on which section 20 of the Planning etc. (Scotland) Act 2006 came into force.]
(2)[F3If no time limit is specified in any grant of listed building consent under subsection (1), the grant shall be deemed to have been made subject to a condition that works in terms of the consent shall be commenced within 5 years from the date of the grant.]
[F3For the purposes of sections 18(1)(a) and 19(1) and (2)(a)—
(a)any such specification as is mentioned in subsection (1)(a), or
(b)the effect of subsection (1) as that subsection applies in consequence of the authority electing not to make such a specification,
is to be treated as a condition subject to which the application is granted.]
(3)Nothing in this section applies to any consent to the retention of works granted under section 7(3).
(4)The date of the granting or of the refusal of an application for listed building consent shall be the date on which the notice of the planning authority’s decision bears to have been signed on behalf of the authority.
Textual Amendments
(1)Any person interested in a listed building with respect to which listed building consent has been granted subject to conditions may apply to the planning authority for the variation or discharge of the conditions.
(2)The application shall indicate what variation or discharge of conditions is applied for and the provisions of sections 9 to 13, 14(3) and 18 to 20 apply to such an application as they apply to an application for listed building consent.
(3)On such an application the planning authority or, as the case may be, the Secretary of State may vary or discharge the conditions attached to the consent, and may add new conditions consequential upon the variation or discharge, as they or he think fit.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: