There are currently no known outstanding effects for the Petroleum Act 1998, Section 17F.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(1)This section applies to controlled petroleum pipelines.
(2)Any person who seeks a right to have things conveyed by a controlled petroleum pipeline of which he is not the owner (“the applicant”) shall, before making an application to the Secretary of State under subsection (5), apply to the owner of the pipeline for the right.
(3)An application under subsection (2) shall be made by giving notice to the owner specifying what is being sought.
(4)Such a notice shall, in particular, specify—
(a)the kind of things to be conveyed (which must be of a kind the pipeline is designed to convey); and
(b)the quantities to be conveyed.
(5)If the owner and the applicant do not reach agreement on the application, the applicant may apply to the Secretary of State for a notice under subsection (9) securing to the applicant the right to have conveyed by the pipeline in respect of which he has made an application to the owner under subsection (2) the quantities specified in the notice under subsection (3) of things of a kind so specified.
(6)The Secretary of State shall not entertain an application under subsection (5) unless he is satisfied that the parties have had a reasonable time in which to reach agreement between themselves on the application under subsection (2).
(7)Where a person applies to the Secretary of State under subsection (5) and the Secretary of State is satisfied as mentioned in subsection (6), the Secretary of State shall—
(a)give notice to the owner of the pipeline and the applicant that he proposes to consider the application; and
(b)after the expiry of 21 days beginning with the date on which notice under paragraph (a) was served, but before considering the application, give them an opportunity of being heard with respect to the application.
(8)When considering the application, the Secretary of State shall (so far as relevant) take into account—
(a)capacity which is or can reasonably be made available in the pipeline in question;
(b)any incompatibilities of technical specification which cannot reasonably be overcome;
(c)difficulties which cannot reasonably be overcome and which could prejudice the efficient, current and planned future production of petroleum;
(d)the owner’s reasonable needs for the transport and processing of petroleum;
(e)the interests of all users and operators of the pipeline;
(f)the need to maintain security and regularity of supplies of petroleum; and
(g)the number of parties involved in the dispute.
(9)Where the Secretary of State is satisfied that, if he served a notice under this subsection, the pipeline in question could be operated in accordance with the notice without prejudicing its efficient operation for the purpose of conveying, on behalf of its owner, the quantities of permitted substances which the owner requires or may reasonably be expected to require, the Secretary of State may serve such a notice on the owner and the applicant.
(10)A notice under subsection (9) may contain such provisions as the Secretary of State considers appropriate for any of the following purposes—
(a)to secure to the applicant the right to have conveyed by the pipeline the quantities specified in the notice under subsection (3) of the things of a kind so specified;
(b)to secure that the exercise of the right is not prevented or impeded;
(c)to regulate the charges which may be made for the conveyance of things by virtue of the right; and
(d)to secure to the applicant the right to have a pipeline of his connected to the pipeline by the applicant or owner.
(11)A notice under subsection (9) may also authorise the owner to recover from the applicant payments by way of consideration for any right mentioned in subsection (10)(a) or (d) of amounts specified in the notice or determined in accordance with the notice.
Textual Amendments
F1Ss. 17A-17H inserted (10.8.2000) by S.I. 2000/1937, reg. 2(4), Sch. 4 para. 4
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: