[F175(1)This paragraph applies where—U.K.

(a)an operator has, for the purposes of the operator's network, installed any electronic communications apparatus, and

(b)the whole or part of the apparatus is at a height of three metres or more above the ground.

(2)The operator must, before the end of the period of three days beginning with the day after that on which the installation is completed, in a secure and durable manner attach a notice—

(a)to every major item of apparatus installed, or

(b)if no major item of apparatus is installed, to the nearest major item of electronic communications apparatus to which the apparatus that is installed is directly or indirectly connected.

(3)A notice attached under sub-paragraph (2)—

(a)must be attached in a position where it is reasonably legible, and

(b)must give the name of the operator and an address in the United Kingdom at which any notice of objection may be given under paragraph 77(5) in respect of the apparatus in question.

(4)Any person giving such a notice at that address in respect of that apparatus is to be treated as having given that address for the purposes of paragraph 91(2).

(5)An operator who breaches the requirements of this paragraph is guilty of an offence and liable on summary conviction to a fine not exceeding level 2 on the standard scale.

(6)In any proceedings for an offence under this paragraph it is a defence for the person charged to prove that the person took all reasonable steps and exercised all due diligence to avoid committing the offence.]

Textual Amendments

F1Sch. 3A inserted (31.7.2017 for the purpose of making regulations under Sch. 3A para. 95, 22.11.2017 but only in relation to Sch. 3A para. 106, 28.12.2017 in so far as not already in force) by Digital Economy Act 2017 (c. 30), s. 118(6), Sch. 1 (with Sch. 2); S.I. 2017/765, reg. 2(ii)(jj); S.I. 2017/1136, reg. 2; S.I. 2017/1286, reg. 2(b)