Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 3


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 18/10/2011
Status:
Point in time view as at 01/03/2005.
Changes to legislation:
Energy Act 2004, Paragraph 3 is up to date with all changes known to be in force on or before 03 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
This section has no associated Explanatory Notes
3(1)Where permission has been granted to bring an appeal against a decision to give a consent, an authorised member of the Commission may, on behalf of the Commission, direct that, pending the determination of the appeal—E+W+S
(a)the consent is not to have effect; or
(b)the consent is not to have effect to such extent as may be specified in the direction.
(2)The power to give a direction under this paragraph is exercisable only where—
(a)an application for its exercise has been made by the applicant for permission or by another person with interests or functions that entitle him, or would have entitled him, to appeal against the decision;
(b)the applicant for the exercise of the power would incur significant costs if the consent were to have effect, or to continue to have effect, before the determination of the appeal; and
(c)the balance of convenience does not otherwise require effect to be given to the consent pending that determination.
(3)That power is exercisable at any time before the determination of the appeal.
(4)A person making an application under this paragraph must notify GEMA.
(5)Before determining whether to grant an application under this paragraph, the authorised member of the Commission must give GEMA an opportunity of making representations about the matter.
(6)In this paragraph “consent” includes an approval or direction.