Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Chapter
PrintThe Whole
Cross Heading
PrintThis
Section
only
Status:
Point in time view as at 01/03/2005. This version of this provision is not valid for this point in time.

Status
Not valid for this point in time generally means that a provision was not in force for the point in time you have selected to view it on.
Changes to legislation:
Energy Act 2004, Section 109 is up to date with all changes known to be in force on or before 06 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Valid from 01/10/2005
109Carrying out of decommissioning programmesU.K.
This section has no associated Explanatory Notes
(1)Where a decommissioning programme is approved by the Secretary of State, it shall be the duty of the person who submitted the programme to secure—
(a)that it is carried out in every respect; and
(b)that all the conditions to which the approval is subject are complied with.
(2)Where a relevant object is subject to a decommissioning programme approved by the Secretary of State, it is an offence for a person to take any measures for decommissioning that object unless he does so—
(a)in accordance with the programme; or
(b)with the agreement of the Secretary of State.