Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Chapter
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 154


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 01/10/2005
Status:
Point in time view as at 01/03/2005. This version of this provision has been superseded.

Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
Energy Act 2004, Section 154 is up to date with all changes known to be in force on or before 03 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
154Energy administration ordersE+W+S
This section has no associated Explanatory Notes
(1)In this Chapter “energy administration order” means an order which—
(a)is made by the court in relation to a protected energy company; and
(b)directs that, while the order is in force, the affairs, business and property of the company are to be managed by a person appointed by the court.
(2)The person appointed in relation to a company for the purposes of an energy administration order is referred to in this Chapter as the energy administrator of the company.
(3)The energy administrator of a company must manage its affairs, business and property, and exercise and perform all his powers and duties as such, so as to achieve the objective set out in section 155.
(4)In relation to an energy administration order applying to a non-GB company, references in this section to the affairs, business and property of the company are references only to its affairs and business so far as carried on in Great Britain and to its property in Great Britain.
(5)In this Chapter—