- Latest available (Revised)
- Point in Time (01/06/2022)
- Original (As enacted)
Version Superseded: 26/10/2023
Point in time view as at 01/06/2022. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Energy Act 2004, Section 157 is up to date with all changes known to be in force on or before 19 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)On hearing an application for an energy administration order, the court has the following powers—
(a)it may make the order;
(b)it may dismiss the application;
(c)it may adjourn the hearing conditionally or unconditionally;
(d)it may make an interim order;
(e)it may treat the application as a winding-up petition and make any order the court could make under section 125 of the 1986 Act (power of court on hearing winding-up petition);
(f)it may make any other order which the court thinks appropriate.
(2)The court may make an energy administration order in relation to a company only if it is satisfied—
(a)that the company is unable to pay its debts;
(b)that it is likely to be unable to pay its debts; or
(c)that, on a petition by the Secretary of State under section 124A of the 1986 Act (petition for winding up on grounds of public interest), it would be just and equitable (disregarding the objective of the energy administration) to wind up the company in the public interest.
(3)The court must not make an energy administration order in relation to a company on the ground set out in subsection (2)(c) unless the Secretary of State has certified to the court that the case is one in which he considers (disregarding the objective of the energy administration) that it would be appropriate for him to petition under section 124A of the 1986 Act.
(4)The court has no power to make an energy administration order in relation to a company which—
(a)is in administration under Schedule B1 to the 1986 Act; or
(b)has gone into liquidation (within the meaning of section 247(2) of that Act).
(5)An energy administration order comes into force—
(a)at the time appointed by the court; or
(b)if no time is so appointed, when the order is made.
(6)An interim order under subsection (1)(d) may, in particular—
(a)restrict the exercise of a power of the company or of its directors; or
(b)make provision conferring a discretion on a person qualified to act as an insolvency practitioner in relation to the company.
(7)Where the company in relation to which an application is made is a non-GB company, the reference in subsection (6)(a) to restricting the exercise of a power of the company or of its directors is a reference only to restricting the exercise of such a power—
(a)within Great Britain; or
(b)in relation to the company’s affairs or business so far as carried on in Great Britain, or to its property in Great Britain.
(8)For the purposes of this section a company is unable to pay its debts if—
(a)it is a company which is deemed to be so unable under section 123 of the 1986 Act (definition of inability to pay debts); or
(b)it is an unregistered company which is deemed, by virtue of any of sections 222 to 224 of that Act, to be so unable for the purposes of section 221 of that Act (winding-up of unregistered companies), or which would be so deemed if it were an unregistered company for the purposes of those sections.
Modifications etc. (not altering text)
C1Pt. 3 Ch. 3: power to modify conferred (31.3.2022 for specified purposes, 1.6.2022 in so far as not already in force) by Nuclear Energy (Financing) Act 2022 (c. 15), ss. 38, 44(1)(c)(2)(c)
C2Ss. 154-171 modified (1.10.2005) by Energy Administration Rules 2005 (S.I. 2005/2483), rules 1, 184 (with rules 3, 187)
C3Ss. 156-167 applied (with modifications) (18.12.2011) by Energy Act 2011 (c. 16), ss. 96(1)-(4), 121(3)
C4Ss. 154-171 modified (7.6.2013) by The Energy Supply Company Administration Rules 2013 (S.I. 2013/1046), rules 1, 205(2)-(4) (with rules 3, 208)
C5Ss. 156-167 applied (with modifications) (23.7.2018) by Smart Meters Act 2018 (c. 14), ss. 4(1)-(4), 14(5)
C6Ss. 154-171 modified (E.W.) (1.8.2020) by The Smart Meter Communication Licensee Administration (England and Wales) Rules 2020 (S.I. 2020/629), rules 1, 3(2)-(4) (with rule 4(1))
C7Ss. 156-167 applied (with modifications) (31.3.2022 for specified purposes, 1.6.2022 in so far as not already in force) by Nuclear Energy (Financing) Act 2022 (c. 15), ss. 33(1)-(5), 44(1)(c)(2)(c)
Commencement Information
I1S. 157 in force at 5.10.2004 by S.I. 2004/2575, art. 2(1), Sch. 1
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: