- Latest available (Revised)
- Point in Time (01/01/2017)
- Original (As enacted)
Version Superseded: 01/04/2017
Point in time view as at 01/01/2017. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Energy Act 2004, Section 95 is up to date with all changes known to be in force on or before 12 October 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)This section applies where—
(a)there is a proposal to construct a renewable energy installation in waters subject to regulation under this section, or to extend or to decommission a renewable energy installation situated in such waters;
(b)there is a proposal to operate a renewable energy installation on completion of its construction in such waters, or of any extension of it in such waters; or
(c)a renewable energy installation is being constructed, extended, operated or decommissioned in such waters.
[F1(1A)This section is subject to section 13 of the Marine and Coastal Access Act 2009 (which transfers certain functions of the Secretary of State to the Marine Management Organisation).]
(2)If the Secretary of State considers it appropriate to do so for the purpose of securing the safety of—
(a)the renewable energy installation or its construction, extension or decommissioning,
(b)other installations in the vicinity of the installation or the place where it is to be constructed or extended,
(c)individuals in or on the installation or other installations in that vicinity, or
(d)vessels in that vicinity or individuals on such vessels,
he may issue a notice declaring that such areas as are specified or described in the notice are to be safety zones for the purposes of this Chapter.
(3)The power of the Secretary of State to issue a notice under this section shall be exercisable by him either—
(a)on an application made to him for the purpose by any person; or
(b)where no such application is made, on his own initiative.
(4)Before issuing a notice under this section which relates, wholly or partly, to—
(a)an area of Scottish waters, or
(b)an area of waters in a Scottish part of a Renewable Energy Zone,
the Secretary of State must consult the Scottish Ministers.
(5)An area may be declared to be a safety zone only if it is an area of waters around or adjacent to a place where a renewable energy installation is to be, or is being, constructed, extended, operated or decommissioned; but a safety zone may extend to waters outside the waters subject to regulation under this section.
(6)A notice under this section—
(a)must identify the renewable energy installation, or proposed renewable energy installation, by reference to which it is issued;
(b)must specify the date on which it is to come into force, or the means by which that date is to be determined;
(c)may contain provision by virtue of which the area of a safety zone varies from time to time by reference to factors specified in, or determinations made in accordance with, the provisions of the notice;
(d)may contain provision imposing prohibitions on the carrying on in a safety zone of activities specified in, or determined in accordance with, the provisions of the notice, or for the imposition of such prohibitions;
(e)may contain provision granting permission for vessels to enter or remain in a safety zone or for persons to carry on prohibited activities, or for the grant of such permissions;
(f)may confer discretions, with respect to the making of determinations for the purposes of such a notice, on such persons as may be specified or described in the notice;
(g)may modify or revoke a previous notice; and
(h)may make different provision in relation to different cases.
(7)Where a notice is issued under this section or a determination is made for the purposes of such a notice, the Secretary of State must either—
(a)himself publish the notice or determination in such manner as he considers appropriate for bringing it, as soon as is reasonably practicable, to the attention of persons likely to be affected by it; or
(b)secure that it is published in that manner—
(i)by the applicant for the notice; or
(ii)in the case of a determination made by a person other than the Secretary of State, by the applicant for the notice or by the person who made the determination.
(8)References in this section to a determination for the purposes of a notice include references to a determination made for those purposes in accordance with the notice, or with regulations under section 96—
(a)to impose a prohibition;
(b)to grant a permission; or
(c)to impose conditions in relation to a permission.
(9)Schedule 16 (which makes provision about the procedure for the declaration of safety zones) has effect.
(10)The waters subject to regulation under this section are—
(a)waters in or adjacent to Great Britain which are between the mean low water mark and the seaward limits of the territorial sea; and
(b)waters within a Renewable Energy Zone.
Textual Amendments
F1S. 95(1A) inserted (1.4.2010) by Marine and Coastal Access Act 2009 (c. 23), ss. 13(7), 324(3); S.I. 2010/298, art. 2, Sch. para. 5 (with art. 4(2))
Modifications etc. (not altering text)
C1S. 95: transfer of functions in part (1.4.2010) by Marine and Coastal Access Act 2009 (c. 23), ss. 13(2)(5), 324(3); S.I. 2010/298, art. 2, Sch. para. 5 (with art. 4(2))
Commencement Information
I1S. 95 in force at 1.10.2005 by S.I. 2005/877, art. 2(2), Sch. 2
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: