- Latest available (Revised)
- Point in Time (24/08/2005)
- Original (As enacted)
Version Superseded: 22/06/2015
Point in time view as at 24/08/2005. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Planning and Compulsory Purchase Act 2004, Section 51 is up to date with all changes known to be in force on or before 28 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Section 91 of the principal Act (limit on duration of planning permission) is amended as follows—
(a)in subsections (1)(a) and (3) for the words “five years” there is substituted “ three years ”;
(b)after subsection (3) there are inserted the following subsections—
“(3A)Subsection (3B) applies if any proceedings are begun to challenge the validity of a grant of planning permission or of a deemed grant of planning permission.
(3B)The period before the end of which the development to which the planning permission relates is required to be begun in pursuance of subsection (1) or (3) must be taken to be extended by one year.
(3C)Nothing in this section prevents the development being begun from the time the permission is granted or deemed to be granted.”
(2)In section 92 of that Act (outline planning permission)—
(a)in subsection (2)(b) sub-paragraph (i) is omitted;
(b)in subsection (2)(b) in sub-paragraph (ii) the words “if later” are omitted;
(c)in subsection (4) “five years” is omitted.
(3)In section 73 of the principal Act (applications to develop land without compliance with existing conditions) after subsection (4) there is inserted the following subsection—
“(5)Planning permission must not be granted under this section to the extent that it has effect to change a condition subject to which a previous planning permission was granted by extending the time within which—
(a)a development must be started;
(b)an application for approval of reserved matters (within the meaning of section 92) must be made.”
(4)Section 18 of the listed buildings Act (limit of duration of listed buildings consent) is amended as follows—
(a)in subsections (1)(a) and (2) for the words “five years” there is substituted “ three years ”;
(b)after subsection (2) there are inserted the following subsections—
“(2A)Subsection (2B) applies if any proceedings are begun to challenge the validity of a grant of listed building consent or of a deemed grant of listed building consent.
(2B)The period before the end of which the works to which the consent relates are required to be begun in pursuance of subsection (1) or (2) must be taken to be extended by one year.
(2C)Nothing in this section prevents the works being begun from the time the consent is granted.”
(5)In section 19 of that Act (variation or discharge of conditions) after subsection (4) there is inserted the following subsection—
“(5)But a variation or discharge of conditions under this section must not—
(a)vary a condition subject to which a consent was granted by extending the time within which the works must be started;
(b)discharge such a condition.”
(6)This section has effect only in relation to applications made under the principal Act or the listed buildings Act which are received by the local planning authority after the commencement of the section.
Commencement Information
I1S. 51 in force at 24.8.2005 for E. by S.I. 2005/2081, art. 2(c) (with art. 4(2))
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: