16.Section 4(1) disapplies the normal consents regime established under the Electricity Act 1989 for the installation of overhead electric lines on land that is within the limits of deviation for the scheduled works or the land required for Crossrail (the “limit of land to be acquired or used”). The limits of deviation and the limit of land to be acquired or used taken together are referred to in these Explanatory Notes as “the Act limits”.

17.Section 4(2) brings into effect Schedule 4, which establishes a replacement consents regime for such lines.

18.Section 4(3) provides that once the consent granted under Schedule 4 is revoked or expires, the line to which it relates will revert to being subject to the Electricity Act 1989.

19.Section 4(4) provides that any consent granted under Schedule 4 by the Secretary of State for Transport and the Secretary of State for Business, Enterprise and Regulatory Reform, acting jointly, may include the grant of deemed planning permission, with or without conditions.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item