SCHEDULES

SCHEDULE 6Acquisition of land shown within limits on deposited plans

Part 2Application of legislation relating to compulsory purchase

Compulsory Purchase Act 1965

3

1

In its application by virtue of paragraph 2, the Compulsory Purchase Act 1965 shall have effect with the following modifications.

2

Section 4 (time for exercise of powers of compulsory purchase) shall be omitted.

3

Section 11(1) (power to enter on and take possession of land the subject of a notice to treat after giving not less than 14 days' notice) shall have effect—

a

in a case where the notice to treat relates only to the acquisition of subsoil or under-surface of land or an easement or other right over land, with the substitution for “fourteen days” of “ one month's ”, and

b

in any other case, with the substitution for “fourteen days” of “ three months' ”.

4

In section 22(2) (expiry of time limit for exercise of power of compulsory acquisition not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” there shall be substituted “ section 6(6) of the Crossrail Act 2008 ”.

5

In Schedule 3 (alternative procedures for obtaining right of entry), paragraph 3(3) (requirement as to sureties in relation to bond for compensation) shall be omitted.