Part 3Nationally significant infrastructure projects

Waste

I130Hazardous waste facilities

1

The construction of a hazardous waste facility is within section 14(1)(p) only if—

a

the facility (when constructed) will be in England,

b

the main purpose of the facility is expected to be the final disposal or recovery of hazardous waste, and

c

the facility is expected to have the capacity specified in subsection (2).

2

The capacity is—

a

in the case of the disposal of hazardous waste by landfill or in a deep storage facility, more than 100,000 tonnes per year;

b

in any other case, more than 30,000 tonnes per year.

3

The alteration of a hazardous waste facility is within section 14(1)(p) only if—

a

the facility is in England,

b

the main purpose of the facility is the final disposal or recovery of hazardous waste, and

c

the alteration is expected to have the effect specified in subsection (4).

4

The effect is—

a

in the case of the disposal of hazardous waste by landfill or in a deep storage facility, to increase by more than 100,000 tonnes per year the capacity of the facility;

b

in any other case, to increase by more than 30,000 tonnes per year the capacity of the facility.

5

The following terms have the same meanings as in the Hazardous Waste (England and Wales) Regulations 2005 (S.I. 2005/894) (see regulation 5 of those regulations)—

  • “disposal”;

  • “hazardous waste”;

  • “recovery”.

6

Deep storage facility” means a facility for the storage of waste underground in a deep geological cavity.