Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Valid from 01/03/2010
(1)The Secretary of State has the function of deciding an application for an order granting development consent where—
(a)in a case within section 74(2), the Secretary of State receives the Panel's report on the application, or
(b)in a case within section 83(2)(b), the Secretary of State receives the single Commissioner's report on the application.
(2)In this Act “decision-maker” in relation to an application for an order granting development consent—
(a)means the Panel that has the function of deciding the application, or
(b)where the Council or the Secretary of State has the function of deciding the application, means the Council or (as the case may be) the Secretary of State.
(1)This section applies in relation to an application for an order granting development consent if the decision-maker is a Panel or the Council.
(2)In deciding the application the Panel or Council must have regard to—
(a)any national policy statement which has effect in relation to development of the description to which the application relates (a “relevant national policy statement”),
[F1(aa)the appropriate marine policy documents (if any), determined in accordance with section 59 of the Marine and Coastal Access Act 2009;]
(b)any local impact report (within the meaning given by section 60(3)) submitted to the Commission before the deadline specified in a notice under section 60(2),
(c)any matters prescribed in relation to development of the description to which the application relates, and
(d)any other matters which the Panel or Council thinks are both important and relevant to its decision.
(3)The Panel or Council must decide the application in accordance with any relevant national policy statement, except to the extent that one or more of subsections (4) to (8) applies.
(4)This subsection applies if the Panel or Council is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the United Kingdom being in breach of any of its international obligations.
(5)This subsection applies if the Panel or Council is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the Panel or Council, or the Commission, being in breach of any duty imposed on it by or under any enactment.
(6)This subsection applies if the Panel or Council is satisfied that deciding the application in accordance with any relevant national policy statement would be unlawful by virtue of any enactment.
(7)This subsection applies if the Panel or Council is satisfied that the adverse impact of the proposed development would outweigh its benefits.
(8)This subsection applies if the Panel or Council is satisfied that any condition prescribed for deciding an application otherwise than in accordance with a national policy statement is met.
(9)For the avoidance of doubt, the fact that any relevant national policy statement identifies a location as suitable (or potentially suitable) for a particular description of development does not prevent one or more of subsections (4) to (8) from applying.
Textual Amendments
F1S. 104(2)(aa) inserted (12.1.2010) by Marine and Coastal Access Act 2009 (c. 23), ss. 58(5), 324(2)(a)
Commencement Information
I1S. 104 partly in force; s. 104 in force for certain purposes at Royal Assent see s. 241
(1)This section applies in relation to an application for an order granting development consent if the decision-maker is the Secretary of State.
(2)In deciding the application the Secretary of State must have regard to—
(a)any local impact report (within the meaning given by section 60(3)) submitted to the Commission before the deadline specified in a notice under section 60(2),
(b)any matters prescribed in relation to development of the description to which the application relates, and
(c)any other matters which the Secretary of State thinks are both important and relevant to the Secretary of State's decision.
Commencement Information
I2S. 105 partly in force; s. 105 in force for certain purposes at Royal Assent see s. 241
Valid from 01/03/2010
(1)In deciding an application for an order granting development consent, the decision-maker may disregard representations if the decision-maker considers that the representations—
(a)are vexatious or frivolous,
(b)relate to the merits of policy set out in a national policy statement, or
(c)relate to compensation for compulsory acquisition of land or of an interest in or right over land.
(2)In this section “representation” includes evidence.
Valid from 01/03/2010
(1)The decision-maker is under a duty to decide an application for an order granting development consent by the end of the period of 3 months beginning with the day after the start day.
(2)The start day is—
(a)in a case where a Panel is the decision-maker, the deadline for the completion of its examination of the application under section 98;
(b)in a case where the Council is the decision-maker, the deadline for the completion of the single Commissioner's examination of the application under section 98;
(c)in a case where the Secretary of State is the decision-maker by virtue of section 103(1), the day on which the Secretary of State receives a report on the application under section 74(2)(b) or 83(2)(b);
(d)in a case where the Secretary of State is the decision-maker by virtue of section 113(2)(b), the deadline for the completion of the Secretary of State's examination of the application under section 113(2)(a).
(3)The appropriate authority may set a date for the deadline under subsection (1) that is later than the date for the time being set.
(4)The appropriate authority is—
(a)in a case where a Panel or the Council is the decision-maker, the person appointed to chair the Commission;
(b)in a case where the Secretary of State is the decision-maker, the Secretary of State.
(5)The power under subsection (3) may be exercised—
(a)more than once in relation to the same deadline;
(b)after the date for the time being set for the deadline.
(6)Where the power under subsection (3) is exercised other than by the Secretary of State—
(a)the person exercising the power must notify the Secretary of State of what has been done and of the reasons for doing it, and
(b)the Commission's report under paragraph 17 of Schedule 1 for the financial year in which the power is exercised must mention and explain what has been done.
(7)Where the power under subsection (3) is exercised by the Secretary of State, the Secretary of State must—
(a)notify each interested party of what has been done and of the reasons for doing it, and
(b)lay before Parliament a report explaining what has been done.
(8)A report under subsection (7)(b) must be published in such form and manner as the Secretary of State thinks appropriate.
(9)“Interested party” means a person who is an interested party in relation to the application for the purposes of Chapter 4 (see section 102).
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: