Part 6Deciding applications for orders granting development consent

Chapter 5Decisions on applications

I1107Timetable for decisions

1

The F4Secretary of State is under a duty to decide an application for an order granting development consent by the end of the period of 3 months beginning F2with—

a

the F5deadline under section 98(3)F3, or

b

(if earlier) the end of the day on which the Secretary of State receives a report on the application under section 74(2)(b) or 83(1)(b).

F62

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3

The F7Secretary of State may set a date for the deadline under subsection (1) that is later than the date for the time being set.

F84

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

5

The power under subsection (3) may be exercised—

a

more than once in relation to the same deadline;

b

after the date for the time being set for the deadline.

F16

Subsection (7) applies where the power under subsection (3) is exercised.

7

The Secretary of State exercising the power must make a statement, to the House of Parliament of which that Secretary of State is a member, announcing the new deadline.

8

A statement under subsection (7) must be published in such form and manner as the Secretary of State considers appropriate.

8A

A statement under subsection (7) may be written or oral.