Planning Act 2008

143Diversion of watercoursesE+W
This section has no associated Explanatory Notes

(1)An order granting development consent may include provision authorising the diversion of any part of a navigable watercourse only if the condition in subsection (2) is met.

(2)The new length of watercourse must be navigable in a reasonably convenient manner by vessels of a kind that are accustomed to using the part of the watercourse which is to be diverted.

(3)In deciding whether the condition in subsection (2) is met, the effect of any bridge or tunnel must be ignored if the construction of the bridge or tunnel is part of the development for which consent is granted by the order granting development consent.

(4)If an order granting development consent includes provision authorising the diversion of any part of a navigable watercourse, the order is also to be taken to authorise the diversion of any tow path or other way adjacent to that part.

Commencement Information

I1S. 143 in force at 1.3.2010 by S.I. 2010/101, art. 4(e) (with art. 6)