Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)The construction or extension of a generating station is within section 14(1)(a) only if the generating station is or (when constructed or extended) is expected to be within subsection (2) [F1, (3), (3A) or (3B)].
(2)A generating station is within this subsection if—
(a)it is in England F2...,
[F3(aa)it does not generate electricity from wind,]
(b)it is not an offshore generating station, and
(c)its capacity is more than 50 megawatts.
(3)A generating station is within this subsection if—
(a)it is an offshore generating station, and
(b)its capacity is more than 100 megawatts.
[F4(3A)A generating station is within this subsection if—
(a)it is in Wales,
(b)it does not generate electricity from wind, and
(c)its capacity is more than 350 megawatts.
(3B)A generating station is within this subsection if—
(a)it is in waters adjacent to Wales up to the seaward limits of the territorial sea, or in the Welsh zone, and
(b)its capacity is more than 350 megawatts.]
[F5(3C)To the extent that an exempt electricity storage facility forms part of a generating station (or is expected to do so, when the generating station is constructed or extended), any capacity provided by the facility is to be disregarded for the purposes of determining whether the generating station is within subsection (2), (3), (3A) or (3B).
(3D)The construction or extension of a generating station is not within section 14(1)(a) to the extent that the generating station comprises or (when constructed or extended) is expected to comprise an exempt electricity storage facility.]
(4)An “offshore” generating station is a generating station that is—
(a)in waters in or adjacent to England F6... up to the seaward limits of the territorial sea, or
(b)in a Renewable Energy Zone, except [F7the Welsh zone or] any part of a Renewable Energy Zone in relation to which the Scottish Ministers have functions.
[F8(5)"Welsh zone” has the meaning given in section 158 of the Government of Wales Act 2006.]
[F9(6)In this section—
“electricity storage facility” means a facility which generates electricity from energy that—
was converted from electricity by that facility, and
is stored within that facility for the purpose of its future reconversion into electricity;
“exempt electricity storage facility” means an electricity storage facility which is not a pumped hydroelectric storage facility;
“pumped hydroelectric storage facility” means an electricity storage facility that stores the gravitational potential energy of water that has been pumped to a higher level so that its return to a lower level can be used to generate electricity.]
Textual Amendments
F1Words in s. 15(1) substituted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(2), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F2Words in s. 15(2)(a) omitted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by virtue of Wales Act 2017 (c. 4), ss. 39(3), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F3S. 15(2)(aa) inserted (5.3.2016) by The Infrastructure Planning (Onshore Wind Generating Stations) Order 2016 (S.I. 2016/306), arts. 1(2), 3 (with arts. 5-8)
F4S. 15(3A)(3B) inserted (31.3.2017 for specified purposes, 1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(4), 71(2)(e) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F5S. 15(3C)(3D) inserted (2.12.2020) by The Infrastructure Planning (Electricity Storage Facilities) Order 2020 (S.I. 2020/1218), arts. 1(2), 3(2) (with arts. 4-7)
F6Words in s. 15(4)(a) omitted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by virtue of Wales Act 2017 (c. 4), ss. 39(5)(a), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F7Words in s. 15(4)(b) inserted (1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(5)(b), 71(4) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F8S. 15(5) inserted (31.3.2017 for specified purposes, 1.4.2018 for specified purposes, 1.4.2019 in so far as not already in force) by Wales Act 2017 (c. 4), ss. 39(6), 71(2)(e) (with Sch. 7 paras. 1, 6, 8); S.I. 2017/1179, regs. 3(h), 5(a)
F9S. 15(6) inserted (2.12.2020) by The Infrastructure Planning (Electricity Storage Facilities) Order 2020 (S.I. 2020/1218), arts. 1(2), 3(3) (with arts. 4-7)
Commencement Information
I1S. 15 in force at 1.3.2010 by S.I. 2010/101, art. 4(a) (with art. 6)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: