- Latest available (Revised)
- Point in Time (22/01/2021)
- Original (As enacted)
Version Superseded: 05/03/2022
Point in time view as at 22/01/2021. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Planning Act 2008, Section 152 is up to date with all changes known to be in force on or before 22 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)This section applies if, by virtue of section 158 or an order granting development consent, there is a defence of statutory authority in civil or criminal proceedings for nuisance in respect of any authorised works.
(2)“Authorised works” are—
(a)development for which consent is granted by an order granting development consent;
(b)anything else authorised by an order granting development consent.
(3)A person by whom or on whose behalf any authorised works are carried out must pay compensation to any person whose land is injuriously affected by the carrying out of the works.
(4)A dispute as to whether compensation under subsection (3) is payable, or as to the amount of the compensation, must be referred to the [F1Upper Tribunal].
(5)Subsection (2) of section 10 of the Compulsory Purchase Act 1965 (c. 56) (limitation on compensation) applies to subsection (3) of this section as it applies to that section.
(6)Any rule or principle applied to the construction of section 10 of that Act must be applied to the construction of subsection (3) of this section (with any necessary modifications).
(7)Part 1 of the Land Compensation Act 1973 (c. 26) (compensation for depreciation of land value by physical factors caused by use of public works) applies in relation to authorised works as if—
(a)references in that Part to any public works were to any authorised works;
(b)references in that Part to the responsible authority were to the person for whose benefit the order granting development consent has effect for the time being;
(c)sections 1(6) and 17 were omitted.
(8)An order granting development consent may not include provision the effect of which is to remove or modify the application of any of subsections (1) to (7).
Textual Amendments
F1Words in s. 152(4) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 293 (with Sch. 5)
Modifications etc. (not altering text)
C1S. 152 applied (26.9.2012) by The Network Rail (Ipswich Chord) Order 2012 (S.I. 2012/2284), arts. 1, 19(5) (with art. 26(2))
C2S. 152 applied (6.11.2012) by The Network Rail (North Doncaster Chord) Order 2012 (S.I. 2012/2635), arts. 1, 25(5) (with art. 35(2))
C3S. 152 applied (21.4.2014) by The Network Rail (Norton Bridge Area Improvements) Order 2014 (S.I. 2014/909), arts. 1, 23(5) (with art. 34(2))
C4S. 152 applied (18.9.2014) by The A556 (Knutsford to Bowdon Improvement) Development Consent Order 2014 (S.I. 2014/2269), arts. 1, 21(5) (with art. 21(6))
C5S. 152 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 19(3)(a)
C6S. 152 applied (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 24(5) (with art. 24(6))
C7S. 152 applied (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 25(5) (with arts. 51, 53)
C8S. 152 applied (18.2.2016) by The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016 (S.I. 2016/73), arts. 1, 22(5) (with arts. 22(6), 37)
C9S. 152 applied (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 24(4) (with arts. 24(5), 39)
C10S. 152 applied (7.9.2016) by The Hornsea Two Offshore Wind Farm Order 2016 (S.I. 2016/844), arts. 1(2), 21(4) (with arts. 21(5), 37, 38)
C11S. 152 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 19(3)(a) (with arts. 19(4), 31)
C12S. 152 applied (29.8.2017) by The East Anglia THREE Offshore Wind Farm Order 2017 (S.I. 2017/826), arts. 1, 18(4) (with arts. 5(9), 18(5), 36, 37, Sch. 8 para. 34)
C13S. 152 applied (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 26(5) (with arts. 4, 37)
C14S. 152 applied (3.10.2018) by The A19/A184 Testos Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 24(5) (with arts. 3(3), 5)
C15S. 152 applied (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 27(4)(5) (with arts. 55, 56)
C16S. 152 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 28(5) (with art. 3(1))
C17S. 152 applied (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 24(5) (with arts. 5, 44)
C18S. 152 applied (22.1.2021) by The Hornsea Three Offshore Wind Farm Order 2020 (S.I. 2020/1656), arts. 1, 21(4) (with arts. 21(5), 40, 41, Sch. 9 Pt. 5 para. 18)
Commencement Information
I1S. 152 in force at 1.3.2010 by S.I. 2010/101, art. 3(h) (with art. 6)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: