204Wales: transitional provision in relation to blighted landE+W
(1)During the transitional period the repeal by PCPA 2004 of paragraphs 1 to 4 of Schedule 13to TCPA 1990 in relation to Wales is subject to subsection (2).
(2)That repeal does not affect anything which is required or permitted to be done for the purposes of Chapter 2 of Part 6 of TCPA 1990 (interests affected by planning proposals: blight) in relation to land falling within any of paragraphs 1, 2, 3 and 4 of Schedule 13 to TCPA 1990.
(3)The transitional period is the period during which—
(a)in the case of land falling within paragraph 1 of Schedule 13 to TCPA 1990, a structure plan continues to be or to be comprised in the development plan for an area in Wales by virtue of Part 3 of Schedule 5 to the Local Government (Wales) Act 1994 (c. 19) and Part 1A of Schedule 2 to TCPA 1990;
(b)in the case of land falling within paragraph 2 of Schedule 13 to TCPA 1990, a local plan continues to be or to be comprised in the development plan for an area in Wales by virtue of Part 3 of Schedule 5 to the Local Government (Wales) Act 1994 and Part 1A of Schedule 2 to TCPA 1990;
(c)in the case of land falling within paragraphs 3 or 4 of Schedule 13 to TCPA 1990, a unitary development plan continues to form part of the development plan for an area in Wales by virtue of article 3(1) and (2) of the PCPA No.6 Order 2005.
(4)In this section “PCPA No.6 Order 2005” means the Planning and Compulsory Purchase Act 2004 (Commencement No.6, Transitional Provisions and Savings) Order 2005 (S.I. 2005/2847).
(5)This section is deemed to have come into force on the same day as the repeal of paragraphs 1 to 4 of Schedule 13 to TCPA 1990 came into force in relation to Wales (see Article 2(e) and (g) of the PCPA No.6 Order 2005).