Part 3Nationally significant infrastructure projects

Water

I127Dams and reservoirs

1

The construction of a dam or reservoir is within section 14(1)(m) only if—

a

the dam or reservoir (when constructed) will be in England,

b

the construction will be carried out by one or more water undertakers, and

F1c

it is expected that—

i

the volume of water to be held back by the dam or stored in the reservoir will exceed 30 million cubic metres, or

ii

the deployable output of the dam or reservoir will exceed 80 million litres per day.

2

The alteration of a dam or reservoir is within section 14(1)(m) only if—

a

the dam or reservoir is in England,

b

the alteration will be carried out by one or more water undertakers, and

F2c

it is expected that—

i

the additional volume of water to be held back by the dam or stored in the reservoir as a result of the alteration will exceed 30 million cubic metres, or

ii

the additional deployable output of the dam or reservoir as a result of the alteration will exceed 80 million litres per day.

3

Water undertaker” means a company appointed as a water undertaker under the Water Industry Act 1991 (c. 56).