This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 09/01/2019.
Changes to legislation:
Planning Act 2008, Section 47 is up to date with all changes known to be in force on or before 02 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
47Duty to consult local communityE+W+S
This section has no associated Explanatory Notes
(1)The applicant must prepare a statement setting out how the applicant proposes to consult, about the proposed application, people living in the vicinity of the land.
(2)Before preparing the statement, the applicant must consult each local authority that is within section 43(1) about what is to be in the statement.
(3)The deadline for the receipt by the applicant of a local authority's response to consultation under subsection (2) is the end of the period of 28 days that begins with the day after the day on which the local authority receives the consultation documents.
(4)In subsection (3) “the consultation documents” means the documents supplied to the local authority by the applicant for the purpose of consulting the local authority under subsection (2).
(5)In preparing the statement, the applicant must have regard to any response to consultation under subsection (2) that is received by the applicant before the deadline imposed by subsection (3).
(6)Once the applicant has prepared the statement, the applicant [must—
(za)make the statement available for inspection by the public in a way that is reasonably convenient for people living in the vicinity of the land,]
(a)[publish,] in a newspaper circulating in the vicinity of the land[, a notice stating where and when the statement can be inspected], and
(b)[publish the statement in such manner] as may be prescribed.
(7)The applicant must carry out consultation in accordance with the proposals set out in the statement.