Search Legislation

Marine and Coastal Access Act 2009

Changes over time for: Cross Heading: Special provisions in certain cases

 Help about opening options

Version Superseded: 01/04/2018

Status:

Point in time view as at 29/08/2017.

Changes to legislation:

Marine and Coastal Access Act 2009, Cross Heading: Special provisions in certain cases is up to date with all changes known to be in force on or before 09 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

Special provisions in certain casesU.K.

78Special procedure for applications relating to harbour worksU.K.

(1)This section has effect in cases where—

(a)a person who proposes to carry on an activity must first make an application for a marine licence to carry on that activity (the “marine licence application”), and

(b)a related application for a harbour order (the “harbour order application”) is or has been made by the person, or the harbour order authority has reason to believe that it will be so made.

(2)A “related application for a harbour order” is an application for an order under section 14 or 16 of the Harbours Act in relation to—

(a)the activity for which the marine licence is required, or

(b)other works to be undertaken in connection with that activity.

(3)In any case where—

(a)both the marine licence application and the harbour order application have been made,

(b)the harbour order authority decides (with the agreement of the Welsh Ministers, if they are the marine licence authority and the Secretary of State is the harbour order authority) that the two applications are to be considered together, and

(c)the harbour order authority has given notice of that decision to the applicant,

the two applications are to be considered together.

(4)Subsection (5) applies in any case where—

(a)one of the applications has been received but not the other,

(b)the harbour order authority decides (with the agreement of the Welsh Ministers, if they are the marine licence authority and the Secretary of State is the harbour order authority) that the two applications are to be considered together, and

(c)the harbour order authority has given notice of that decision to the applicant.

(5)In any such case—

(a)the application that has been received is not to be considered until the other application has also been received,

(b)the two applications are to be considered together, and

(c)the condition in subsection (3)(b) is to be regarded as satisfied by virtue of subsection (4)(b),

but this is subject to any provision that may be made by virtue of subsection (6)(c) or (d).

(6)The Secretary of State may by order do any of the following—

(a)make provision falling within subsection (7) for cases where subsection (3) applies;

(b)make provision falling within subsection (7) for cases where subsection (5) applies;

(c)make provision falling within subsection (7) or (8) for cases where the harbour order authority (with the agreement of the Welsh Ministers, if they are the marine licence authority and the Secretary of State is the harbour order authority) comes to the conclusion that the marine licence application is not going to be made;

(d)make provision falling within subsection (7) or (8) for cases where the harbour order authority comes to the conclusion that the harbour order application is not going to be made.

(7)The provision that may be made by virtue of this subsection is—

(a)provision that such procedural provisions of this Part as are specified in the order are not to apply to the marine licence application;

(b)provision that such procedural provisions of the Harbours Act as are so specified are to apply to that application instead;

(c)provision modifying the provisions of the Harbours Act in their application by virtue of paragraph (b).

(8)The provision that may be made by virtue of this subsection is provision modifying—

(a)such procedural provisions of this Part as are specified in the order, or

(b)such procedural provisions of the Harbours Act as are specified in the order.

(9)In this section—

  • the harbour order authority” means—

    (a)

    the Secretary of State, in any case where the harbour order application falls (or would fall) to be determined by the Secretary of State;

    (b)

    the Welsh Ministers, in any case where the harbour order application falls (or would fall) to be determined by the Welsh Ministers;

  • the Harbours Act” means the Harbours Act 1964 (c. 40);

  • the marine licence authority” means—

    (a)

    the Secretary of State, in any case where the marine licence application falls (or would fall) to be made to the Secretary of State;

    (b)

    the Welsh Ministers, in any case where the marine licence application falls (or would fall) to be made to the Welsh Ministers;

  • procedural provisions” means any provisions for or in connection with the procedure for determining an application.

Commencement Information

I1S. 78 partly in force; s. 78 in force for specified purposes at Royal Assent see s. 324(1)(c)

I2S. 78 in force at 6.4.2011 in so far as not already in force by S.I. 2011/556, art. 3(2)(a)

79Special procedure for applications relating to certain electricity worksU.K.

(1)This section has effect in cases where a person who proposes to carry on an activity must first make both—

(a)an application for a marine licence to carry on that activity (the “marine licence application”), and

(b)a related application for a generating station consent (the “generating station application”).

(2)A “related application for a generating station consent” is an application for a consent under section 36 of the Electricity Act (consent for construction etc of generating stations) in relation to—

(a)the activity for which the marine licence is required, or

(b)other works to be undertaken in connection with that activity.

(3)In any case where—

(a)both the marine licence application and the generating station application have been made,

(b)the generating station authority decides (with the agreement of the Welsh Ministers, if they are the marine licence authority and the Secretary of State is the generating station authority) that the two applications are to be considered together, and

(c)the generating station authority has given notice of that decision to the applicant,

the two applications are to be considered together.

(4)Subsection (5) applies in any case where—

(a)one of the applications has been received but not the other,

(b)the generating station authority decides (with the agreement of the Welsh Ministers, if they are the marine licence authority and the Secretary of State is the generating station authority) that the two applications are to be considered together, and

(c)the generating station authority has given notice of that decision to the applicant.

(5)In any such case—

(a)the application that has been received is not to be considered until the other application has also been received,

(b)the two applications are to be considered together, and

(c)the condition in subsection (3)(b) is to be regarded as satisfied by virtue of subsection (4)(b),

but this is subject to any provision that may be made by virtue of subsection (6)(c) or (d).

(6)The Secretary of State may by order do any of the following—

(a)make provision falling within subsection (7) for cases where subsection (3) applies;

(b)make provision falling within subsection (7) for cases where subsection (5) applies;

(c)make provision falling within subsection (7) or (8) for cases where the generating station authority (with the agreement of the Welsh Ministers, if they are the marine licence authority and the Secretary of State is the generating station authority) comes to the conclusion that the marine licence application is not going to be made;

(d)make provision falling within subsection (7) or (8) for cases where the generating station authority comes to the conclusion that the generating station application is not going to be made.

(7)The provision that may be made by virtue of this subsection is—

(a)provision that such procedural provisions of this Part as are specified in the order are not to apply to the marine licence application;

(b)provision that such procedural provisions of the Electricity Act as are so specified are to apply to that application instead;

(c)provision modifying the provisions of the Electricity Act in their application by virtue of paragraph (b).

(8)The provision that may be made by virtue of this subsection is provision modifying—

(a)such procedural provisions of this Part as are specified in the order, or

(b)such procedural provisions of the Electricity Act as are specified in the order.

(9)In this section—

  • the Electricity Act” means the Electricity Act 1989 (c. 29);

  • generating station authority” means—

    (a)

    the Secretary of State, in any case where the generating station application falls (or would fall) to be determined by the Secretary of State;

    (b)

    the Scottish Ministers, in any case where the generating station application falls (or would fall) to be determined by the Scottish Ministers;

  • the marine licence authority” means—

    (a)

    the Secretary of State, in any case where the marine licence application falls (or would fall) to be made to the Secretary of State;

    (b)

    the Scottish Ministers, in any case where the marine licence application falls (or would fall) to be made to the Scottish Ministers;

    (c)

    the Welsh Ministers, in any case where the marine licence application falls (or would fall) to be made to the Welsh Ministers;

  • procedural provisions” means any provisions for or in connection with the procedure for determining an application.

Commencement Information

I3S. 79 partly in force; s. 79 in force for specified purposes at Royal Assent see s. 324(1)(c)

I4S. 79 in force at 6.4.2011 in so far as not already in force by S.I. 2011/556, art. 3(2)(a)

[F179ASpecial procedure for applications relating to certain electricity works (Northern Ireland)U.K.

(1)This section has effect in cases where a person who proposes to carry on an activity must first make both—

(a) an application to the Department of the Environment in Northern Ireland (“ the Department ”) for a marine licence to carry on that activity (the “marine licence application”), and

(b)a related application for a generating station consent (the “generating station application”).

(2) A “related application for a generating station consent” is an application to DETI for a consent under Article 39 of the Electricity Order (consent for construction, etc. of generating stations) in relation to—

(a)the activity for which the marine licence is required, or

(b)other works to be undertaken in connection with that activity.

(3)In any case where—

(a)both the marine licence application and the generating station application have been made,

(b)DETI decides (with the agreement of the Department) that the two applications are to be considered together, and

(c)DETI has given notice of that decision to the applicant,

the two applications are to be considered together.

(4)Subsection (5) applies in any case where—

(a)one of the applications has been received but not the other,

(b)DETI decides (with the agreement of the Department) that the two applications are to be considered together, and

(c)DETI has given notice of that decision to the applicant.

(5)In any such case—

(a)the application that has been received is not to be considered until the other application has also been received,

(b)the two applications are to be considered together, and

(c)the condition in subsection (3)(b) is to be regarded as satisfied by virtue of subsection (4)(b),

but this is subject to any provision that may be made by virtue of subsection (6)(c) or (d).

(6)The Department may by order do any of the following—

(a)make provision falling within subsection (7) for cases where subsection (3) applies;

(b)make provision falling within subsection (7) for cases where subsection (5) applies;

(c)make provision falling within subsection (7) or (8) for cases where DETI (with the agreement of the Department) comes to the conclusion that the marine licence application is not going to be made;

(d)make provision falling within subsection (7) or (8) for cases where DETI comes to the conclusion that the generating station application is not going to be made.

(7)The provision that may be made by virtue of this subsection is—

(a)provision that such procedural provisions of this Part as are specified in the order are not to apply to the marine licence application;

(b)provision that such procedural provisions of the Electricity Order as are so specified are to apply to that application instead;

(c)provision modifying the provisions of the Electricity Order in their application by virtue of paragraph (b).

(8)The provision that may be made by virtue of this subsection is provision modifying—

(a)such procedural provisions of this Part as are specified in the order, or

(b)such procedural provisions of the Electricity Order as are specified in the order.

(9)In this section—

  • DETI ” means the Department of Enterprise, Trade and Investment in Northern Ireland;

  • the Electricity Order ” means the Electricity (Northern Ireland) Order 1992;

  • procedural provisions ” means any provisions for or in connection with the procedure for determining an application. ]

Textual Amendments

F1S. 79A inserted (N.I.) (18.9.2013) by Marine Act (Northern Ireland) 2013 (c. 10), ss. 42, 49 (with ss. 1(1), 46(3), 47)

80Electronic communications apparatusU.K.

(1)A licensing authority must not grant a marine licence to carry on any activity which amounts to or involves the exercise of a right conferred by paragraph 11 of the Electronic Communications Code unless it is satisfied that adequate compensation arrangements have been made.

(2)For the purposes of subsection (1) “adequate compensation arrangements” are adequate arrangements for compensating any persons—

(a)who appear to that authority to be owners of interests in the tidal water or lands on, under or over which the right is to be exercised,

(b)for any loss or damage sustained by those persons in consequence of the activity being carried on.

(3)In paragraph 11 of the Electronic Communications Code omit—

(a)sub-paragraphs (3) to (10);

(b)in sub-paragraph (11), the definition of “remedial works”.

(4)In this section “the Electronic Communications Code” means the code set out in Schedule 2 to the Telecommunications Act 1984 (c. 12).

Commencement Information

I5S. 80 in force at 6.4.2011 by S.I. 2011/556, art. 3(2)(a)

81Submarine cables on the continental shelfU.K.

(1)Nothing in this Part applies to anything done in the course of laying or maintaining an offshore stretch of exempt submarine cable.

(2)Where subsection (1) has effect in relation to part (but not the whole) of an exempt submarine cable—

(a)the appropriate licensing authority must grant any application made to it for a marine licence for the carrying on of a licensable marine activity in the course of laying any inshore stretch of the cable, and

(b)nothing in this Part applies to anything done in the course of maintaining any inshore stretch of the cable.

(3)A licensing authority has the same powers to attach conditions to a marine licence required to be granted by virtue of subsection (2) as it has in relation to a marine licence not required to be so granted.

(4)In the application of this section in relation to any cable—

  • inshore stretch” means any of the cable which is laid, or proposed to be laid, within the seaward limits of the territorial sea;

  • offshore stretch” means any of the cable which is laid, or proposed to be laid, beyond the seaward limits of the territorial sea.

(5)For the purposes of this section a submarine cable is “exempt” unless it is a cable constructed or used in connection with any of the following—

(a)the exploration of the UK sector of the continental shelf;

(b)the exploitation of the natural resources of that sector;

(c)the operations of artificial islands, installations and structures under the jurisdiction of the United Kingdom;

(d)the prevention, reduction or control of pollution from pipelines.

(6)In this section—

  • natural resources” means—

    (a)

    the mineral and other non-living resources of the sea bed and subsoil,together with

    (b)

    living organisms belonging to sedentary species;

  • living organisms belonging to sedentary species” means organisms which, at the harvestable stage, are either—

    (a)

    immobile on or under the sea bed, or

    (b)

    unable to move except in constant physical contact with the sea bed or the subsoil.

Commencement Information

I6S. 81 in force at 6.4.2011 by S.I. 2011/556, art. 3(2)(a)

82Structures in, over or under a main riverU.K.

(1)Section 109 of the Water Resources Act 1991 (c. 57) (structures in, over or under a main river) is amended as follows.

(2)After subsection (6) insert—

(7)Subsections (1) to (3) above shall not apply to any work if—

(a)carrying out the work is a licensable marine activity,

(b)the Agency considers that, in view of the terms and conditions that will be included in the marine licence, the provisions of those subsections may be dispensed with, and

(c)the Agency issues a notice to that effect to the applicant for the marine licence.

(8)In subsection (7) above “licensable marine activity” and “marine licence” have the same meaning as in Part 4 of the Marine and Coastal Access Act 2009..

Commencement Information

I7S. 82 in force at 6.4.2011 by S.I. 2011/556, art. 3(2)(a)

83Requirements for Admiralty consent under local legislationU.K.

(1)If, in the case of any particular work,—

(a)a marine licence is needed for the carrying out of the work,

(b)Admiralty consent for the carrying out of the work would also be required (apart from this subsection) by virtue of any local legislation, and

(c)the Secretary of State considers that, in view of the need for a marine licence, the requirement for Admiralty consent for the carrying out of the work may be dispensed with, and issues a notice to that effect,

the requirement for Admiralty consent does not apply in relation to that work.

(2)In subsection (1)—

  • Admiralty consent” means the consent of the Admiralty, whether alone or jointly with any other government department;

  • local legislation” means—

    (a)

    a local Act, or

    (b)

    any such Act and any notice given and published by the Admiralty under section 9 of the Harbours Transfer Act 1862 (c. 69).

Commencement Information

I8S. 83 in force at 6.4.2011 by S.I. 2011/556, art. 3(2)(a)

84Byelaws for flood defence and drainage purposesU.K.

(1)Schedule 25 to the Water Resources Act 1991 (c. 57) (byelaw making powers of the Environment Agency) is amended as follows.

(2)In paragraph 5 (byelaws for flood defence and drainage purposes) after sub-paragraph (3) insert—

(3A)If, in any particular case,—

(a)a marine licence is needed for the carrying on of any activity,

(b)before that activity may be carried on, the consent of the Agency would also be required (apart from this sub-paragraph) by virtue of any byelaw under this paragraph, and

(c)the Agency considers that, in view of the terms and conditions that will be included in the marine licence, the requirement for the consent of the Agency may be dispensed with, and issues a notice to that effect,

the requirement for the consent of the Agency does not apply in relation to the carrying on of that activity.

(3B)In sub-paragraph (3A) “marine licence” has the same meaning as in Part 4 of the Marine and Coastal Access Act 2009..

Commencement Information

I9S. 84 in force at 6.4.2011 by S.I. 2011/556, art. 3(2)(a)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources