Part 4Marine licensing
C1C2Chapter 1Marine licences
Pt. 4 Ch. 1 modified (E.W.S.) (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 11, Sch. 13 Pt. 2 Sch. 14 Pts. 2 (with arts. 12, 13, Pt. 2 para. 6, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4, Sch. 12 paras. 19)
73BF1Applications under section 73A: requirement for permission
1
No proceedings may be taken in respect of an application under section 73A(1) unless the Inner House of the Court of Session has granted permission for the application to proceed.
2
The Court may grant permission under subsection (1) for an application to proceed only if it is satisfied that—
a
the applicant can demonstrate a sufficient interest in the subject matter of the application, and
b
the application has a real prospect of success.
3
The Court may grant permission under subsection (1) for an application to proceed—
a
subject to such conditions as the Court thinks fit, or
b
only on such of the grounds specified in the application as the Court thinks fit.
Pt. 4 Ch. 1 modified (E.W.S.) (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 27 (with art. 30)