SCHEDULES
C1SCHEDULE 1Risk Management: Designation of Features
Annotations:
Modifications etc. (not altering text)
Designation
I14
1
If the following conditions are satisfied, a designating authority may designate for the purposes of this Schedule—
a
a structure, or
b
a natural or man-made feature of the environment.
2
Condition 1 is that the designating authority thinks the existence or location of the structure or feature affects—
a
a flood risk, or
b
a coastal erosion risk.
3
Condition 2 is that the designating authority has flood or coastal erosion risk management functions in respect of the risk which is affected.
4
Condition 3 is that the structure or feature is not designated by another authority for the purposes of this Schedule.
5
Condition 4 is that the owner of the structure or feature is not a designating authority.
Sch. 1 excluded (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), art. 1, Sch. 19 Pt. 1 para. 11