- Latest available (Revised)
- Point in Time (01/10/2010)
- Original (As enacted)
No versions valid at: 01/10/2010
Point in time view as at 01/10/2010. This version of this cross heading contains provisions that are not valid for this point in time.
There are currently no known outstanding effects for the Flood and Water Management Act 2010, Cross Heading: Water Resources Act 1991.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Valid from 01/04/2011
40E+WThe Water Resources Act 1991 is amended as follows.
41E+WSection 106 (obligation to carry out flood defence functions through committees) is repealed.
Prospective
42E+WIn section 110 (main river structures: applications for consent) in subsection (1) for “and the amount of that fee shall be £50 or such other sum as may be prescribed” substitute “ and the amount of the fee shall be determined in accordance with a prescribed charging scheme ”.
43(1)Section 118 (special duties with respect to flood defence revenues) is amended as follows.E+W
(2)In subsection (1)—
(a)for “flood defence functions” substitute “ flood and coastal erosion risk management functions, within the meaning of Part 1 of the Flood and Water Management Act 2010, ”, and
(b)for “local flood defence district” substitute “ flood risk management region ”.
(3)In subsection (2) for “local flood defence district” substitute “ flood risk management region ”.
(4)Omit subsection (3)(b) (and the “or” before it).
(5)In subsection (4) for “local flood defence district” substitute “ flood risk management region ”.
(6)In subsection (5)—
(a)in paragraph (b) for “flood defence district” substitute “ flood risk management region ”, and
(b)for “local flood defence district” substitute “ flood risk management region ”.
(7)Omit subsection (6).
(8)At the end add—
“(7)In this section “flood risk management region” means the region of a Regional Flood and Coastal Committee, within the meaning of section 22 of the Flood and Water Management Act 2010.”
44E+WSection 133 (power to authorise the Agency to issue levies) is repealed.
Valid from 19/07/2011
45E+WIn section 159 (powers to lay pipes in streets) after subsection (1) insert—
“(1A)The Agency may carry out work within subsection (1)(a) to (c) if—
(a)it thinks the work desirable having regard to the national flood and coastal erosion risk management strategies under sections 7 and 8 of the Flood and Water Management Act 2010, and
(b)the purpose of the work is to manage a flood risk (within the meaning of that Act) from (i) the sea, or (ii) a main river.”
Valid from 19/07/2011
46E+WIn section 160 (power to lay pipes in other land) after subsection (1) insert—
“(1A)The Agency may carry out work within subsection (1)(a) to (c) if—
(a)it thinks the work desirable having regard to the national flood and coastal erosion risk management strategies under sections 7 and 8 of the Flood and Water Management Act 2010, and
(b)the purpose of the work is to manage a flood risk (within the meaning of that Act) from (i) the sea, or (ii) a main river.”
Valid from 19/07/2011
47(1)Section 165 (powers to carry out works) is amended as follows.E+W
(2)For subsection (1) substitute—
“(1)The Agency may—
(a)carry out flood risk management work within subsection (1D)(a) to (f) if Conditions 1 and 2 are satisfied;
(b)carry out flood risk management work within subsection (1D)(g) or (h) if Condition 1 is satisfied.
(1A)Condition 1 is that the Agency considers the work desirable having regard to the national flood and coastal erosion risk management strategies under sections 7 and 8 of the Flood and Water Management Act 2010.
(1B)Condition 2 is that the purpose of the work is to manage a flood risk (within the meaning of that Act) from—
(a)the sea, or
(b)a main river.
(1C)In subsection (1B)(b) the reference to a main river includes a reference to a lake, pond or other area of water which flows into a main river.
(1D)In this section “flood risk management work” means anything done—
(a)to maintain existing works (including buildings or structures) including cleansing, repairing or otherwise maintaining the efficiency of an existing watercourse or drainage work;
(b)to operate existing works (such as sluicegates or pumps);
(c)to improve existing works (including buildings or structures) including anything done to deepen, widen, straighten or otherwise improve an existing watercourse, to remove or alter mill dams, weirs or other obstructions to watercourses, or to raise, widen or otherwise improve a drainage work;
(d)to construct or repair new works (including buildings, structures, watercourses, drainage works and machinery);
(e)for the purpose of maintaining or restoring natural processes;
(f)to monitor, investigate or survey a location or a natural process;
(g)to reduce or increase the level of water in a place;
(h)to alter or remove works.”
(3)In subsection (2) omit “, irrespective of whether the works are in connection with a main river,”.
(4)In subsection (5)—
(a)omit “in connection with a main river”, and
(b)at the end add “ under this section ”.
(5)In subsection (7) omit from “; and subsections (2)” to the end.
(6)The heading becomes “General powers to carry out works”.
48E+WAfter section 204(2)(c) (exceptions to prohibition on disclosure of information) insert—
“(ca)for the purpose of complying with a request under section 14 of the Flood and Water Management Act 2010;”.
Valid from 19/07/2011
49E+WIn Schedule 25 (byelaws) for paragraph 5(1)(a) and (b) substitute—
“for any of Purposes 1 to 4.
(1A)Purpose 1 is to secure the efficient working of a drainage system.
(1B)Purpose 2 is to regulate the effects on the environment of a drainage system.
(1C)Purpose 3 is to secure the effectiveness of flood risk management work within the meaning of section 165.
(1D)Purpose 4 is to secure the effectiveness of works done in reliance on section 38 or 39 of the Flood and Water Management Act 2010 (incidental flooding or coastal erosion).”
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: