SCHEDULES
SCHEDULE 3Sustainable Drainage
Enforcement
14
1
The Minister shall by order provide for the enforcement of the requirement for approval in paragraph 7(1).
2
An order may, in particular, make provision about cases where—
a
construction is commenced without a drainage system having been approved,
b
conditions of approval are breached, or
c
construction does not conform to the approved proposals.
3
An order may, in particular, provide for—
a
notices (including enforcement notices, stop notices, temporary notice and breach of condition notices),
b
applications to a court or tribunal,
c
powers (including (i) discretionary powers conferred on the Minister or specified authorities, (ii) powers of entry, (iii) powers of inspection, and (iv) powers to undertake and charge for remedial work),
d
offences of failure to comply with the regulations or notices under them,
e
financial penalties,
f
rights of appeal, and
g
compensation.
4
An order may apply (with or without modification) or make provision similar to a provision of the Town and Country Planning Act 1990.
5
An order—
a
may not be made by the Secretary of State unless a draft has been laid before and approved by resolution of each House of Parliament, and
b
may not be made by the Welsh Ministers unless a draft has been laid before and approved by resolution of the National Assembly for Wales.