Search Legislation

Flood and Water Management Act 2010

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As enacted)
 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Flood plans

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the Flood and Water Management Act 2010, Cross Heading: Flood plans. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Flood plansE+W

20(1)Section 12A (flood plans) is amended as follows.E+W

(2)In subsection (1) omit the words from “setting” to the end.

(3)After section 12A(1) insert—

(1A)A flood plan is a document—

(a)giving information about the areas that may be flooded in the event of an uncontrolled escape of water from the large raised reservoir,

(b)specifying the action that the undertaker would take in order to prevent an uncontrolled escape of water, and

(c)specifying the action that the undertaker would take in order to control or mitigate the effects of a flood.

Commencement Information

I1Sch. 4 para. 20 in force at 30.7.2013 for E. by S.I. 2013/1590, art. 3(b)

I2Sch. 4 para. 20 in force at 1.4.2016 for W. by S.I. 2016/79, art. 2(d)

21E+WAfter section 12A insert—

12AAFlood plans: preparation

(1)This section applies where an undertaker is directed to prepare a flood plan under section 12A.

(2)The undertaker must prepare a flood plan in consultation with the appointed engineer.

(3)The undertaker may not provide a copy of, or publish, a flood plan in accordance with a direction under section 12A(2)(d) or (e) unless the appointed engineer has certified that the requirements of a direction under section 12A(2)(a) and (b) are satisfied.

(4)The undertaker must test a flood plan at such times and in such manner as may be directed by the appointed engineer.

(5)In the event of flooding, or if flooding is reasonably expected to occur, the undertaker must implement the flood plan without delay.

(6)The undertaker—

(a)must keep a flood plan under review, and

(b)may revise a flood plan.

(7)The undertaker must revise the flood plan in accordance with the directions of the appointed engineer.

(8)The following apply to a revision of a flood plan as they apply to a flood plan—

(a)subsections (2) to (7), and

(b)any requirements of a direction under section 12A.

(9)In this section “appointed engineer” means—

(a)in the case of a high-risk reservoir, the supervising engineer, and

(b)in any other case, the engineer appointed for the purposes of this section.

Commencement Information

I3Sch. 4 para. 21 in force at 30.7.2013 for E. by S.I. 2013/1590, art. 3(b)

I4Sch. 4 para. 21 in force at 1.4.2016 for W. by S.I. 2016/79, art. 2(d)

22(1)Section 19 (references) is amended as follows.E+W

(2)After subsection (1) insert—

(1A)If an engineer determines that the requirements of a direction under section 12A(2)(a) and (b) are not satisfied for the purposes of section 12AA(3), the undertaker may refer the matter to a referee in accordance with rules under this section.

(3)In subsection (2) after “recommendation” insert “ or determination ”.

(4)In subsections (3) and (4) for “this section” substitute “ subsection (1) ”.

(5)After subsection (4) insert—

(4A)A referee under subsection (1A) may direct the engineer to issue a certificate for the purposes of section 12AA(3).

Commencement Information

I5Sch. 4 para. 22 in force at 1.10.2011 for specified purposes by S.I. 2011/2204, art. 3(1)(f)

I6Sch. 4 para. 22 in force at 30.7.2013 for E. so far as not already in force by S.I. 2013/1590, art. 3(b)

I7Sch. 4 para. 22 in force at 1.4.2016 for W. in so far as not already in force by S.I. 2016/79, art. 2(d)

23(1)Section 20 (reports, certificates etc.) is amended as follows.E+W

(2)In subsection (4)(c) omit “modifying any such report as is mentioned in paragraph (b) above”.

(3)After subsection (4)(g) (inserted by paragraph 17(6)) add—

(h)any direction given under section 12AA(4) or (7).

Commencement Information

I8Sch. 4 para. 23 in force at 30.7.2013 for E. by S.I. 2013/1590, art. 3(b)

I9Sch. 4 para. 23 in force at 1.4.2016 for W. by S.I. 2016/79, art. 2(d)

24E+WIn section 22 (criminal liability) after subsection (1AD) (inserted by paragraph 19) insert—

(1AE)An undertaker who fails to comply with section 12AA(4), (6)(a) or (7) is guilty of an offence and liable—

(a)on conviction on indictment, to a fine, or

(b)on summary conviction, to a fine not exceeding the statutory maximum.

(1AF)An undertaker who fails to comply with section 12AA(5) is guilty of an offence and liable on summary conviction to a fine not exceeding level 5 on the standard scale.

Commencement Information

I10Sch. 4 para. 24 in force at 30.7.2013 for E. by S.I. 2013/1590, art. 3(b)

I11Sch. 4 para. 24 in force at 1.4.2016 for W. by S.I. 2016/79, art. 2(d)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources