Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(1)A lead local flood authority for an area in England must develop, maintain, apply and monitor a strategy for local flood risk management in its area (a “local flood risk management strategy”).
(2)In subsection (1) “local flood risk” means flood risk from—
(a)surface runoff,
(b)groundwater, and
(c)ordinary watercourses.
(3)In subsection (2)(c) the reference to an ordinary watercourse includes a reference to a lake, pond or other area of water which flows into an ordinary watercourse.
(4)The strategy must specify—
(a)the risk management authorities in the authority's area,
(b)the flood and coastal erosion risk management functions that may be exercised by those authorities in relation to the area,
(c)the objectives for managing local flood risk (including any objectives included in the authority's flood risk management plan prepared in accordance with the Flood Risk Regulations 2009),
(d)the measures proposed to achieve those objectives,
(e)how and when the measures are expected to be implemented,
(f)the costs and benefits of those measures, and how they are to be paid for,
(g)the assessment of local flood risk for the purpose of the strategy,
(h)how and when the strategy is to be reviewed, and
(i)how the strategy contributes to the achievement of wider environmental objectives.
(5)The strategy must be consistent with the national flood and coastal erosion risk management strategy for England under section 7.
(6)A lead local flood authority must consult the following about its local flood risk management strategy—
(a)risk management authorities that may be affected by the strategy (including risk management authorities in Wales), and
(b)the public.
(7)A lead local flood authority must publish a summary of its local flood risk management strategy (including guidance about the availability of relevant information).
(8)A lead local flood authority may issue guidance about the application of the local flood risk management strategy in its area.
(9)A lead local flood authority must have regard to any guidance issued by the Secretary of State about—
(a)the local flood risk management strategy, and
(b)guidance under subsection (8).
Commencement Information
I1S. 9 in force at 1.10.2010 for E. by S.I. 2010/2169, art. 4, Sch.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: