Search Legislation

Energy Act 2013

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Power purchase agreement scheme

 Help about opening options

Alternative versions:

Status:

Point in time view as at 15/06/2017.

Changes to legislation:

There are currently no known outstanding effects for the Energy Act 2013, Cross Heading: Power purchase agreement scheme. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Power purchase agreement schemeE+W+S

50Power to modify licence conditions etc to facilitate investment in electricity generationE+W+S

(1)The Secretary of State may modify—

(a)a condition of a particular licence under section 6(1)(d) of EA 1989 (supply licences);

(b)the standard conditions incorporated in licences under that provision by virtue of section 8A of that Act;

(c)a document maintained in accordance with the conditions of licences under section 6(1)(d) of that Act, or an agreement that gives effect to a document so maintained.

(2)The Secretary of State may exercise the power in subsection (1) only for the purpose of facilitating investment in electricity generation by means of a power purchase agreement scheme.

(3)For the purposes of this section and section 51—

(a)a power purchase agreement scheme is a scheme established by supply licence conditions and regulations under section 51 for promoting the availability to electricity generators of power purchase agreements, and

(b)power purchase agreement” means an arrangement under which a licensed supplier agrees to purchase electricity generated by an electricity generator at a discount to a prevailing market price.

For this purpose, “supply licence condition” means any condition, document or agreement of a kind mentioned in subsection (1).

(4)Provision that may be made under subsection (1) in relation to a power purchase agreement scheme includes provision—

(a)as to the eligibility of an electricity generator to enter into a power purchase agreement under the scheme;

(b)as to the terms of any power purchase agreement to be entered into under the scheme, including provision—

(i)for determining the price at which electricity is to be purchased under the agreement (including provision for determining a market price and the amount of a discount at any time);

(ii)as to the duration of any such agreement;

(c)as to the circumstances in which a licensed supplier is or may be required or permitted to enter, or offer to enter, into a power purchase agreement under the scheme;

(d)for the provision of information in connection with the scheme.

(5)Provision within subsection (4)(c) includes provision for determining which licensed supplier or suppliers is or are to be required or permitted to enter, or offer to enter, into a power purchase agreement with an electricity generator in any particular case.

(6)Such provision may in particular include provision for the licensed supplier or suppliers in question to be determined—

(a)by a process involving a determination or determinations by one or more of the following—

(i)the Secretary of State;

(ii)the Authority;

(iii)the electricity generator;

(b)by auction or other competitive process;

and provision that may be made by virtue of paragraph (b) includes provision as to the circumstances in which a licensed supplier is or may be required or permitted to participate in an auction or other process.

(7)For the purposes of this section and section 51, “licensed supplier” means the holder of a licence under section 6(1)(d) of EA 1989.

51Power purchase agreement scheme: regulationsE+W+S

(1)The Secretary of State may by regulations make provision, in connection with any modifications made under section 50, for or in connection with a power purchase agreement scheme.

(2)Any such regulations may in particular—

(a)make provision for apportioning amongst licensed suppliers, or any of them, all or any part of the value of any or all of the costs or benefits of any licensed supplier in connection with the scheme;

(b)confer functions on the Secretary of State or the Authority (which may include provision for directions to be given to the Authority by the Secretary of State);

(c)make provision for the delegation of functions conferred on the Secretary of State or the Authority by the regulations or by virtue of section 50;

(d)include provision for obligations imposed by the regulations on licensed suppliers to be enforceable by the Authority as if they were relevant requirements on a regulated person for the purposes of section 25 of EA 1989;

(e)make provision about the provision of information in connection with the scheme.

(3)Provision that may be included in regulations under this section by virtue of subsection (2)(a) includes, in particular, provision—

(a)for requiring licensed suppliers to pay a levy to the Authority at specified times;

(b)specifying how such a levy is to be calculated;

(c)conferring an entitlement on a licensed supplier to receive a payment from the Authority.

(4)Provision which may be included in regulations by virtue of subsection (3) includes provision for the Secretary of State or the Authority to determine what is to be taken into account as a cost or benefit of any licensed supplier in connection with the scheme and its value.

(5)Regulations under this section may—

(a)include incidental, supplementary and consequential provision;

(b)make transitory or transitional provision or savings;

(c)make different provision for different cases or circumstances or for different purposes;

(d)make provision subject to exceptions.

(6)Before making any regulations under this section, the Secretary of State must consult—

(a)licensed suppliers,

(b)the Authority, and

(c)such other persons as the Secretary of State considers it appropriate to consult.

(7)Subsection (6) may be satisfied by consultation before, as well as by consultation after, the passing of this Act.

(8)Regulations under this section must be made by statutory instrument.

(9)An instrument containing regulations under this section is subject to annulment in pursuance of a resolution of either House of Parliament.

52Power purchase agreement scheme: disclosure of informationE+W+S

In section 105 of the Utilities Act 2000 (general restrictions on disclosure of information)—

(a)in subsection (1)(a), after “2010” insert “ or section 50 or 51 of the Energy Act 2013 ”;

(b)in subsection (3)(a), after “2010” insert “ , section 50 or 51 of the Energy Act 2013 ”.

53Principal objective and general duties: power purchase agreement schemeE+W+S

Sections 3A to 3D of EA 1989 (principal objective and general duties) apply in relation to functions of the Secretary of State or the Authority conferred by or by virtue of section 50 or 51, or section 54 so far as it relates to a power purchase agreement scheme, as they apply in relation to functions under Part 1 of that Act.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources