55Closure of support under the renewables obligation

This section has no associated Explanatory Notes

(1)After section 32L of EA 1989 insert—

32LARenewables obligation closure order

(1)The Secretary of State may make a renewables obligation closure order.

(2)A renewables obligation closure order is an order which provides that no renewables obligation certificates are to be issued under a renewables obligation order in respect of electricity generated after a specified date.

(3)Provision made under subsection (2) may specify different dates in relation to different cases or circumstances.

(4)The cases or circumstances mentioned in subsection (2) may in particular be described by reference to—

(a)accreditation of a generating station, or

(b)the addition of generating capacity to a generating station.

(5)A renewables obligation closure order may include provision about—

(a)the meaning of “accreditation” and “generating capacity” in subsection (4);

(b)when generating capacity is to be treated as added to a generating station for the purposes of that subsection.

(6)References in this section to a renewables obligation order are references to any renewables obligation order made under section 32 (whenever made, and whether or not made by the Secretary of State).

(7)Power to make provision in a renewables obligation order (and any provision contained in such an order) is subject to provision contained in a renewables obligation closure order; but this section is not otherwise to be taken as affecting power to make provision in a renewables obligation order of the kind mentioned in subsection (2).

(8)Section 32K applies in relation to a renewables obligation closure order as it applies in relation to a renewables obligation order (and subsection (3) above is not to be taken as limiting the application of that section).

32LBRenewables obligation closure orders: procedure

(1)Before making a renewables obligation closure order, the Secretary of State must consult—

(a)the Authority,

(b)the Council,

(c)such generators of electricity from renewable sources as the Secretary of State considers appropriate, and

(d)such other persons, if any, as the Secretary of State considers appropriate.

(2)The requirement to consult may be satisfied by consultation before, as well as consultation after, the passing of the Energy Act 2013.

(3)A renewables obligation closure order is not to be made unless a draft of the instrument containing it has been laid before and approved by a resolution of each House of Parliament.

(2)In section 32M(1) of EA 1989 (interpretation of sections 32 to 32M)—

(a)for “32L” substitute “32LB”;

(b)after the definition of “renewables obligation order” insert—

  • “renewables obligation closure order” is to be construed in accordance with section 32LA;;

(c)in the definition of “specified”, after “renewables obligation order” insert “or a renewables obligation closure order”.

(3)In section 106 of EA 1989 (regulations and orders), in subsection (2)(b) after “32,” insert “32LA,”.

(4)In Article 56(1) of the Energy (Northern Ireland) Order 2003 (S.I. 2003/419 (N.I. 6)) (power to amend Part 7 of that Order to take account of amendments of corresponding Great Britain provisions), the reference to amendments made to sections 32 to 32C of EA 1989 includes a reference to subsections (1) and (2) of this section.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Show Explanatory Notes for Sections: Displays relevant parts of the explanatory notes interweaved within the legislation content.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources