Defence Reform Act 2014

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Section 16

 Help about opening options

Version Superseded: 05/12/2014

Alternative versions:

Status:

Point in time view as at 14/07/2014. This version of this provision has been superseded. Help about Status

Changes to legislation:

Defence Reform Act 2014, Section 16 is up to date with all changes known to be in force on or before 09 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

16Pricing of contracts: supplementaryU.K.

This section has no associated Explanatory Notes

(1)Single source contract regulations may specify circumstances in which, if the Secretary of State and the primary contractor so agree—

(a)the price determined in accordance with section 15 is to be taken as a target price, and

(b)the total price payable under the contract is subject to adjustment by reference to any difference between—

(i)the amount of the primary contractor's actual allowable costs under the contract, and

(ii)the amount of the estimated allowable costs used for the purpose of determining the target price.

(2)The amount of any adjustment by virtue of subsection (1)(b) must be determined—

(a)by agreement between the Secretary of State, or an authorised person, and the primary contractor, or

(b)by the SSRO, where the matter is referred to it by the Secretary of State, an authorised person or the primary contractor.

(3)Section 21 (final price adjustment) does not apply to a contract in a case where an agreement of a kind mentioned in subsection (1) has effect.

Commencement Information

I1S. 16 in force at 14.7.2014 for specified purposes by S.I. 2014/1751, art. 4(c)