Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 4


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
No versions valid at: 23/09/2016
Status:
Point in time view as at 23/09/2016. This version of this cross heading contains provisions that are not valid for this point in time.

Status
Not valid for this point in time generally means that a provision was not in force for the point in time you have selected to view it on.
Changes to legislation:
Housing and Planning Act 2016, Paragraph 4 is up to date with all changes known to be in force on or before 01 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Valid from 03/02/2017
This section has no associated Explanatory Notes
4(1)Section 5A of the Land Compensation Act 1961 (relevant valuation date) is amended as follows.E+W
(2)After subsection (5) insert—
“(5A)If—
(a)the acquiring authority enters on and takes possession of land in pursuance of a notice of entry given as mentioned in paragraph 12 of Schedule 2A to the Compulsory Purchase Act 1965 (“the original land”),
(b)the acquiring authority are subsequently required by a determination under paragraph 27 of Schedule 2A to the Compulsory Purchase Act 1965 to take additional land, and
(c)the acquiring authority enters on and takes possession of that additional land,
the authority is deemed for the purposes of subsection (3)(a) to have entered on and taken possession of the additional land when it entered on and took possession of the original land.”
(3)In subsection (6), for “Subsection (5) also applies” substitute “ Subsections (5), (5A) and (5B) also apply ”.