- Latest available (Revised)
- Original (As enacted)
There are currently no known outstanding effects for the High Speed Rail (London - West Midlands) Act 2017, Part 3.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Modifications etc. (not altering text)
C1Sch. 33 Pt. 3: functions transferred (3.5.2023) by The Secretaries of State for Energy Security and Net Zero, for Science, Innovation and Technology, for Business and Trade, and for Culture, Media and Sport and the Transfer of Functions (National Security and Investment Act 2021 etc) Order 2023 (S.I. 2023/424), arts. 1(2), 9(5) (with art. 17)
32(1)The following provisions of this Part have effect, unless otherwise agreed in writing between the nominated undertaker, or the Secretary of State as the case may be, and an operator of an electronic communications code network.U.K.
(2)In this Part—
“"alternative apparatus”” means apparatus provided in replacement of electronic communications apparatus in connection with the construction of the authorised works;
“"the appropriate Ministers”” means the Secretary of State for Transport and [F1the Secretary of State for Science, Innovation and Technology] acting jointly;
“"the authorised works”” means the works authorised by this Act;
“"construction”” includes installation (and “"construct”” is to be construed accordingly);
“"electronic communications code”” means the electronic communications code contained in [F2Schedule 3A to the Communications Act 2003];
““operator””, ““electronic communications apparatus””, and ““electronic communications code network”” have the meanings given by paragraph 1(1) of Schedule 17 to the Communications Act 2003.
Textual Amendments
F1Words in Sch. 33 para. 32(2) substituted (3.5.2023) by The Secretaries of State for Energy Security and Net Zero, for Science, Innovation and Technology, for Business and Trade, and for Culture, Media and Sport and the Transfer of Functions (National Security and Investment Act 2021 etc) Order 2023 (S.I. 2023/424), art. 1(2), Sch. para. 19(3)(c) (with art. 17)
F2Words in Sch. 33 para. 32(2) substituted (coming into force in accordance with of the amending S.I.) by The Communications Act 2003 and the Digital Economy Act 2017 (Consequential Amendments to Primary Legislation) Regulations 2017 (S.I. 2017/1285), reg. 1(1), Sch. 1 para. 13(2)(a)
33(1)Subject to sub-paragraph (2), [F3Part 10] of the electronic communications code applies for the purposes of the authorised works.U.K.
(2)[F4Parts 6 and 10] of the electronic communications code do not apply for the purposes of the authorised works—
(a)insofar as such works are regulated by the New Roads and Street Works Act 1991 or any regulation made under that Act,
(b)where the nominated undertaker exercises a right under subsection (4)(b) of section 272 of the Town and Country Planning Act 1990 or under an order made under that section to remove electronic communications apparatus, or
(c)in respect of any matter regulated by sub-paragraphs (3) to (8) of paragraph 35.
Textual Amendments
F3Words in Sch. 33 para. 33(1) substituted (coming into force in accordance with of the amending S.I.) by The Communications Act 2003 and the Digital Economy Act 2017 (Consequential Amendments to Primary Legislation) Regulations 2017 (S.I. 2017/1285), reg. 1(1), Sch. 1 para. 13(2)(b)(i)
F4Words in Sch. 33 para. 33(2) substituted (coming into force in accordance with of the amending S.I.) by The Communications Act 2003 and the Digital Economy Act 2017 (Consequential Amendments to Primary Legislation) Regulations 2017 (S.I. 2017/1285), reg. 1(1), Sch. 1 para. 13(2)(b)(ii)
34U.K.The temporary stopping up or diversion of any highway under paragraph 6 of Schedule 4 does not affect any right of an operator under [F5Part 8] of the electronic communications code in respect of any apparatus which at the time of the stopping up or diversion is in the highway.
Textual Amendments
F5Words in Sch. 33 para. 34 substituted (coming into force in accordance with of the amending S.I.) by The Communications Act 2003 and the Digital Economy Act 2017 (Consequential Amendments to Primary Legislation) Regulations 2017 (S.I. 2017/1285), reg. 1(1), Sch. 1 para. 13(2)(c)
35(1)Where a highway is stopped up under paragraph 2 or 3 of Schedule 4, any operator of an electronic communications code network whose electronic communications apparatus is under, over, in, on, along or across that highway may exercise the same rights of access in order to inspect, maintain, adjust, repair or alter that apparatus as if this Act had not been passed, but this is subject to sub-paragraph (2).U.K.
(2)Nothing in sub-paragraph (1) affects any right of the nominated undertaker or the operator to require removal of that apparatus under this Part or the power of the nominated undertaker to alter or remove apparatus in accordance with paragraph 23 of the electronic communications code.
(3)The nominated undertaker must give not less than 28 days' notice of its intention to stop up any highway under paragraph 2 or 3 of Schedule 4 to any operator of an electronic communications code network whose apparatus is under, over, in, on, along or across the highway.
(4)Where a notice under sub-paragraph (3) has been given, the operator, if it reasonably considers that it is necessary for the safe and efficient operation and maintenance of the apparatus, may, and if reasonably requested so to do by the nominated undertaker in the notice, must, as soon as reasonably practicable after the service of the notice—
(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the operator may reasonably determine and have power to place it, or
(b)provide other apparatus in substitution for the existing apparatus and place it in such other position as described in paragraph (a).
(5)Subject to the following provisions of this paragraph the nominated undertaker must pay to any operator of an electronic communications code network an amount equal to the cost reasonably incurred by the operator in or in connection with—
(a)the execution of relocation works required in consequence of the stopping up of the highway, and
(b)the doing of any other work or thing rendered necessary by the execution of relocation works.
(6)Sub-paragraph (7) applies where—
(a)in the course of the execution of relocation works under sub-paragraph (4)—
(i)apparatus of better type, greater capacity or greater dimensions is placed in substitution for existing apparatus of worse type, smaller capacity or smaller dimensions, except where this has been solely due to using the nearest currently available type, capacity or dimension, or
(ii)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which existing apparatus was, and
(b)the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the nominated undertaker, or, in default of agreement, is not determined to be necessary in consequence of the construction of the authorised works in order to ensure the continued efficient operation of the electronic communications code network of the operator.
(7)If the execution of the relocation works involves cost exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this paragraph would be payable to the operator by virtue of sub-paragraph (5) is to be reduced by the amount of that excess.
(8)For the purposes of sub-paragraphs (6) and (7)—
(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus except in a case where the apparatus as so extended provides more than an equivalent service, and
(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole (in either case of such type, capacity and dimensions as is reasonably appropriate) is to be treated as if it also had been agreed or had been so determined.
(9)The amount which apart from this sub-paragraph would be payable to an operator in respect of works by virtue of sub-paragraph (5) (and having regard, where it applies, to sub-paragraph (7)) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than seven and a half years earlier so as to confer on the operator any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
(10)Sub-paragraphs (5) to (9) do not apply where the authorised works constitute major transport works or major highway works for the purpose of Part 3 of the New Roads and Street Works Act 1991 (including that provision as applied by paragraph 8 of Schedule 4 to this Act), but instead—
(a)the allowable costs of any relocation works are to be determined in accordance with section 85 of that Act (sharing of costs of necessary measures) and any regulations for the time being having effect under that section, and
(b)the allowable costs are to be borne by the nominated undertaker and the operator in such proportions as may be prescribed by any such regulations.
36(1)Where the nominated undertaker or the Secretary of State affords to an operator facilities and rights for the construction, maintenance, repair, renewal and inspection of alternative apparatus on land held or used, or intended for use, by the nominated undertaker for the purposes of its undertaking under this Act or held by the Secretary of State, those facilities and rights must be granted upon such terms and conditions as may be agreed between the nominated undertaker or, as the case may be, the Secretary of State, and the operator or, in default of agreement, determined in accordance with paragraph 39.U.K.
(2)In determining such terms and conditions, a person making a determination under paragraph 39 must have regard to any template provisions issued by the appropriate Ministers and determined in accordance with sub-paragraph (3); and must—
(a)give effect to all reasonable requirements of the nominated undertaker for ensuring the safety and efficient operation of the authorised works and for securing any subsequent alterations or adaptations of the alternative apparatus which may be required to prevent interference with any proposed works of the nominated undertaker or the use of the same; and
(b)have regard to the operator's ability to fulfil its service obligations.
(3)For the purposes of determining the matters under sub-paragraph (2) the appropriate Ministers must consult the operators to which paragraph 36 may apply on the form of the proposed template provisions, and any objections to the form of those provisions which have not been resolved within six months after this Act comes into force must be referred to an independent person acting as an expert appointed to make a final determination as to the form of the template provisions.
(4)The independent person making a determination under sub-paragraph (3) is to be appointed by the President of the Royal Institution of Chartered Surveyors and in making that determination that person must have regard to the matters specified in sub-paragraph (2)(a) and (b).
(5)If the facilities and rights to be afforded by the nominated undertaker or the Secretary of State in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted are more or less favourable on the whole to the operator than the facilities, rights, terms and conditions applying to the apparatus to be removed, compensation must be paid to or by the nominated undertaker or the Secretary of State to or by the operator in respect of the difference as is reasonable having regard to all the circumstances of the case.
37(1)Sub-paragraph (2) applies where, by reason of the construction of the authorised works or any subsidence resulting from any of those works—U.K.
(a)damage is caused to any electronic communications apparatus, other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works,
(b)damage is caused to property of the operator of an electronic communications code network, or
(c)there is any interruption in the supply of the service provided by the operator.
(2)The nominated undertaker must—
(a)bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply,
(b)make reasonable compensation to the operator for loss sustained by it, and
(c)indemnify the operator against all claims, demands, proceedings, or damages which may be made or taken against, or recovered from, the operator, by reason of any such damage or interruption.
But this is subject to sub-paragraphs (3) to (5).
(3)Sub-paragraph (2) does not apply in connection with any apparatus in respect of which the relations between the nominated undertaker and the operator are regulated by the provisions of Part 3 of the New Roads and Street Works Act 1991.
(4)Nothing in sub-paragraph (2) is to impose any liability on the nominated undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of the operator, its officers, servants, contractors or agents.
(5)The operator must give the nominated undertaker reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand is to be made without the consent of the nominated undertaker which, if it withholds such consent, is to have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
(6)This paragraph applies instead of paragraph 14 of Schedule 2 in relation to the exercise of the powers of paragraphs 2 to 6 of that Schedule.
38U.K.In any case where Network Rail Infrastructure Limited (“Network Rail“) is the nominated undertaker the provisions of this Part have effect subject to any existing agreement between Network Rail and an operator relating to apparatus laid or erected on land belonging to Network Rail.
39(1)Any dispute arising between the nominated undertaker and an operator under this Part is to be determined by arbitration if—U.K.
(a)the parties agree, or
(b)the dispute relates to the amount of any sum payable under this Part,
but is otherwise to be determined by a person appointed by the appropriate Ministers.
(2)Any person appointed by the appropriate Ministers under sub-paragraph (1) must, in determining any dispute arising under this Part, have regard to such matters as may be specified by the appropriate Ministers on making the appointment.
(3)The costs and fees of the person determining the dispute and the costs of the parties to the dispute are to be allocated between the parties as that person may direct.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: