Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
6(1)For the purposes of the works authorised by this Act, the nominated undertaker may—U.K.
(a)temporarily stop up or alter or divert any highway or part of a highway;
(b)for any reasonable time divert traffic from, and prevent persons passing along, any highway or part of a highway;
(c)break up or interfere with any highway or part of a highway (including any sewer, drain or tunnel in it);
(d)temporarily remove any street furniture in or beside a highway.
(2)The nominated undertaker must provide reasonable access for pedestrians going to or from premises abutting on a highway affected by the exercise of the powers under sub-paragraph (1) (a) to (c) if there would otherwise be no such access.
(3)Before exercising the powers under sub-paragraph (1) in relation to a highway, and to an extent, specified in table 3 in Part 4 of this Schedule, the nominated undertaker must consult the relevant authority.
(4)The purpose of consultation under sub-paragraph (3) is to ensure public safety and, so far as reasonably practicable, to reduce public inconvenience.
(5)Before exercising the powers under sub-paragraph (1) in relation to a highway, or to an extent, not specified in table 3, the nominated undertaker must obtain the consent in writing of the relevant authority.
(6)Consent under sub-paragraph (5) must not be unreasonably withheld, but may be given subject to such conditions as the relevant authority may reasonably require in the interest of public safety or convenience.
(7)If a relevant authority which receives an application for consent under sub-paragraph (5) fails to notify the applicant of its decision on the application before the end of 28 days beginning with the date on which the application was made, it is to be treated as having granted the application.
(8)In the case of the powers in sub-paragraph (1)(a) to (c), sub-paragraph (7) has effect in relation to an application for consent which relates to—
(a)a GLA side road (within the meaning of the Road Traffic Regulation Act 1984), or
(b)a road which is designated under section 60(1) or 61(1) of the Traffic Management Act 2004 (roads in Greater London which are strategic roads),
as if for ““28”” there were substituted “ 42 ”.
(9)Any dispute with a relevant authority about consent under sub-paragraph (5) must be referred to arbitration if the parties so agree, but must otherwise be determined by the Secretary of State.
(10)There is no need to reinstate a highway or part of a highway in relation to which any of the powers under sub-paragraph (1) (a) to (c) has been exercised where the exercise of the power comes to an end on the exercise, in relation to the highway or part, of the power under paragraph 2(1) or 3(1).
(11)In this paragraph—
“"relevant authority”” means—
the highway authority, in the case of the powers in sub-paragraph (1)(a) to (c);
the owner of the street furniture, in the case of the power in sub-paragraph (1)(d);
“"street furniture”” includes traffic signs, street lighting and bus shelters.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: