Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1(1)This paragraph has effect in relation to the Ancient Monuments and Archaeological Areas Act 1979.U.K.
(2)Section 2 (control of works affecting scheduled monuments) does not apply to works authorised by this Act.
(3)The powers of entry under the following provisions are not exercisable in relation to land used for or in connection with the carrying out of any of the works authorised by this Act—
section 6(1) (entry to ascertain condition of scheduled monument);
section 6A(1) (entry to enforce control of works affecting scheduled monument);
section 26 (entry to record matters of archaeological or historical interest).
(4)The provisions of the Act with respect to the functions of a person as a guardian by virtue of the Act, and the provisions of any agreement under section 17 (agreement concerning ancient monuments and land in their vicinity), have effect subject to the powers under this Act with respect to works.
(5)Section 19 (public access to monuments under public control) does not apply in relation to a monument which is closed by the nominated undertaker for the purposes of, in connection with or in consequence of the carrying out of any of the works authorised by this Act.
(6)Regulations under section 19(3) or (4A) (which may include provision prohibiting or regulating acts which would tend to injure or disfigure a monument or its amenities or to disturb the public in their enjoyment of it) do not apply to anything done in exercise of the powers under this Act with respect to works.
(7)The power under section 19(6) (power to refuse admission to monuments under public control) is not exercisable so as to prevent or restrict the exercise of the powers under this Act with respect to works.
(8)In section 25 (treatment of ancient monuments)—
(a)subsection (2) (superintendence by Commission) does not authorise the superintendence of the carrying out of any of the works authorised by this Act, and
(b)subsection (3) (power of Commission to charge for advice under subsection (1)) does not apply in relation to advice given in connection with the carrying out of any of those works.
(9)Section 28 (offence of damaging certain ancient monuments) does not apply to anything done in exercise of the powers under this Act with respect to works.
(10)Section 35 (notice required of operations in areas of archaeological importance) does not apply to operations carried out in exercise of the powers under this Act with respect to works.
(11)Section 39(1) (power to investigate in advance of operations notice any site which may be acquired compulsorily) has effect as if operations carried out in exercise of the powers under this Act with respect to works were exempt operations for the purposes of that provision.
(12)Section 42(1) (prohibition on use of metal detectors in protected places without consent) does not apply to the use of a metal detector for the purposes of or in connection with the exercise of the powers under this Act with respect to works.
(13)Section 42(3) (prohibition on removal without consent of object discovered by use of a metal detector in a protected place) does not apply to the removal of objects discovered by the use of a metal detector for the purposes of or in connection with the exercise of the powers under this Act with respect to works.
2(1)The consent of the nominated undertaker is required for the exercise of the power of entry under section 36(1) of the National Heritage Act 1983 (entry to obtain information about ancient monuments and historic buildings for the purposes of the records kept by the Commission) in relation to land used, or intended for use, for or in connection with the carrying out of any of the works authorised by this Act.U.K.
(2)Consent for the purposes of sub-paragraph (1)—
(a)must not be unreasonably withheld;
(b)may be granted subject to compliance with any reasonable requirements or conditions imposed for reasons of safety or for the purpose of preventing interference with or delay to the works.
(3)Section 36(6) of the National Heritage Act 1983 (which, in relation to land on which works are being carried out, regulates the exercise of the power under section 36(1) to enter land to obtain information) does not apply in relation to land on which works authorised by this Act are being carried out.
(4)Any dispute under this paragraph must be referred to arbitration if the parties so agree, but must otherwise be determined by the Secretary of State for Transport and [F1the Secretary of State for Culture, Media and Sport] acting jointly.
Textual Amendments
F1Words in Sch. 19 para. 2(4) substituted (3.5.2023) by The Secretaries of State for Energy Security and Net Zero, for Science, Innovation and Technology, for Business and Trade, and for Culture, Media and Sport and the Transfer of Functions (National Security and Investment Act 2021 etc) Order 2023 (S.I. 2023/424), art. 1(2), Sch. para. 20(2) (with art. 17)
Modifications etc. (not altering text)
C1Sch. 19 para. 2(4): functions transferred (3.5.2023) by The Secretaries of State for Energy Security and Net Zero, for Science, Innovation and Technology, for Business and Trade, and for Culture, Media and Sport and the Transfer of Functions (National Security and Investment Act 2021 etc) Order 2023 (S.I. 2023/424), arts. 1(2), 13(7) (with art. 17)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: