Works
1Power to construct and maintain works for Phase 2a of High Speed 2
1
The nominated undertaker may construct and maintain the works specified in Schedule 1, being—
a
works for the construction of a railway between—
i
a junction with Phase One of High Speed 2 near Fradley Wood in Staffordshire, and
ii
a junction with the West Coast Main Line near Crewe in Cheshire,
b
other railway works which are required for the purposes of—
i
the railway mentioned in paragraph (a), or
ii
a high speed railway transport system of which that railway forms or is to form part, and
c
works consequent on, or incidental to, works within paragraph (a) or (b).
2
In this Act, the works specified in Schedule 1 are called the “scheduled works”.
3
References in this Act to “Phase 2a of High Speed 2” are to the railway mentioned in subsection (1)(a).
4
In subsection (1)(a), “Phase One of High Speed 2” has the same meaning as in the High Speed Rail (London - West Midlands) Act 2017 (see section 1(3) of that Act).