Part 5E+WOther provision about safety, standards etc

Remediation of certain defectsE+W

120Meaning of “relevant defect”E+W

(1)This section applies for the purposes of sections 122 to 125 and Schedule 8.

(2)Relevant defect”, in relation to a building, means a defect as regards the building that—

(a)arises as a result of anything done (or not done), or anything used (or not used), in connection with relevant works, and

(b)causes a building safety risk.

(3)In subsection (2)relevant works” means any of the following—

(a)works relating to the construction or conversion of the building, if the construction or conversion was completed in the relevant period;

(b)works undertaken or commissioned by or on behalf of a relevant landlord or management company, if the works were completed in the relevant period;

(c)works undertaken after the end of the relevant period to remedy a relevant defect (including a defect that is a relevant defect by virtue of this paragraph).

“The relevant period” here means the period of 30 years ending with the time this section comes into force.

(4)In subsection (2) the reference to anything done (or not done) in connection with relevant works includes anything done (or not done) in the provision of professional services in connection with such works.

(5)For the purposes of this section—

Commencement Information

I1S. 120 in force at 28.6.2022, see s. 170(3)(a)