Search Legislation

Procurement Act 2023

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: CHAPTER 4

 Help about opening options

Alternative versions:

Status:

This version of this chapter contains provisions that are prospective. Help about Status

Close

Status

The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:

  1. where the provision (Part, Chapter or section) has never come into force or;
  2. where the text of the provision is subject to change, but no date has yet been appointed by the appropriate person or body for those changes to come into force.

Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.

Changes to legislation:

Procurement Act 2023, CHAPTER 4 is up to date with all changes known to be in force on or before 09 July 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

Prospective

CHAPTER 4U.K.Award under frameworks

45FrameworksU.K.

(1)A contracting authority may award a public contract in accordance with a framework.

(2)A “framework” is a contract between a contracting authority and one or more suppliers that provides for the future award of contracts by a contracting authority to the supplier or suppliers.

(3)Unless subsection (4) applies, a framework may only provide for the future award of a public contract following a competitive selection process.

(4)A framework may provide for the future award of a public contract without competition between suppliers—

(a)in circumstances where only one supplier is party to the framework, or

(b)if the framework sets out—

(i)the core terms of the public contract, and

(ii)an objective mechanism for supplier selection.

(5)A framework must include the following information—

(a)a description of goods, services or works to be provided under contracts awarded in accordance with the framework;

(b)the price payable, or mechanism for determining the price payable, under such contracts;

(c)the estimated value of the framework;

(d)any selection process to be applied on the award of contracts;

(e)the term of the framework (see section 47);

(f)the contracting authorities entitled to award public contracts in accordance with the framework;

(g)whether the framework is awarded under an open framework (see section 49).

(6)A framework may not—

(a)permit the award of a public contract to an excluded supplier, or

(b)prevent a contracting authority from requesting additional information from suppliers before awarding a contract.

(7)A framework may provide for the charging of fees at a fixed percentage of the estimated value of any contract awarded to the supplier in accordance with the framework.

(8)This section does not apply in relation to the award of—

(a)a concession contract, or

(b)a framework.

(9)Subsections (3) to (5) do not apply to a framework that is a light touch contract (see section 9(5)).

Commencement Information

I1S. 45 not in force at Royal Assent, see s. 127(2)

46Frameworks: competitive selection processU.K.

(1)A competitive selection process may provide for conditions of participation only if the contracting authority is satisfied that the conditions are a proportionate means of ensuring that suppliers party to the framework have—

(a)the legal and financial capacity to perform the contract, or

(b)the technical ability to perform the contract.

(2)In this section, a “condition of participation” means a condition that a supplier must satisfy in order to be awarded a public contract in accordance with the framework.

(3)A condition set under subsection (1)(a) may not—

(a)require the submission of audited annual accounts, except from suppliers who are, or were, required to have the accounts audited in accordance with Part 16 of the Companies Act 2006 or an overseas equivalent;

(b)require insurance relating to the performance of the contract to be in place before the award of the contract.

(4)A condition set under subsection (1)(b) may relate to suppliers’ qualifications, experience or technical ability, but may not—

(a)require suppliers to have been awarded a contract under the framework or by a particular contracting authority,

(b)break the rules on technical specifications in section 56, or

(c)require particular qualifications without allowing for their equivalents.

(5)When considering whether a condition is proportionate for the purposes of subsection (1), a contracting authority must have regard to the nature, complexity and cost of the public contract.

(6)A condition of participation may require the provision of evidence that is verifiable by a person other than the supplier.

(7)If a supplier does not satisfy a condition of participation, the contracting authority may exclude the supplier from participating in, or progressing as part of, the competitive selection process.

(8)A competitive selection process may provide for the assessment of proposals, but only by reference to one or more of the award criteria against which tenders were assessed in awarding the framework.

(9)The award criteria may be refined for the purposes of subsection (8).

(10)In this section, a “competitive selection process” means a competitive selection process for the award of a public contract in accordance with a framework.

(11)This section does not apply to a framework that is a light touch contract.

Commencement Information

I2S. 46 not in force at Royal Assent, see s. 127(2)

47Frameworks: maximum termU.K.

(1)The term of a framework may not exceed—

(a)in the case of a defence and security framework or a utilities framework, eight years, and

(b)otherwise, four years.

(2)Subsection (1) does not apply if the contracting authority considers the nature of the goods, services or works to be supplied under contracts awarded in accordance with the framework means that a longer term is required.

(3)If a contracting authority relies on subsection (2) in awarding a framework with a term exceeding four or eight years, the contracting authority must set out its reasons in the tender or transparency notice for the framework.

(4)In this section—

(a)“a defence and security framework” is a framework which does not provide for the future award of public contracts other than defence and security contracts;

(b)“a utilities framework” is a framework which does not provide for the future award of public contracts other than utilities contracts.

(5)This section does not apply in relation to—

(a)a framework awarded under an open framework (see section 49),

(b)a framework awarded by a private utility, or

(c)a framework that is a light touch contract (see section 9(5)).

Commencement Information

I3S. 47 not in force at Royal Assent, see s. 127(2)

48Frameworks: implied termsU.K.

(1)It is an implied term of every framework that a contracting authority may exclude a supplier that is an excluded supplier or has, since the award of the framework, become an excludable supplier from participating in any selection process run in relation to the award of a contract under the framework.

(2)For the purposes of the term in subsection (1), the reference to a supplier becoming an excludable supplier includes a reference to—

(a)a supplier becoming an excludable supplier on the basis of a discretionary exclusion ground that—

(i)did not apply before award of the contract, or

(ii)applied before award of the contract by reference to different circumstances, and

(b)a contracting authority discovering that, before award of the contract, the supplier was an excludable supplier.

(3)Before excluding a supplier that is an excluded or excludable supplier only by virtue of an associated person, the contracting authority must give the supplier reasonable opportunity to replace the associated person.

(4)Any term purporting to restrict or override the term implied by subsection (1) is without effect.

Commencement Information

I4S. 48 not in force at Royal Assent, see s. 127(2)

49Open frameworksU.K.

(1)An “open framework” is a scheme of frameworks that provides for the award of successive frameworks on substantially the same terms.

(2)An open framework must provide—

(a)for the award of a framework at least once during—

(i)the period of three years beginning with the day of the award of the first framework in the scheme, and

(ii)each period of five years beginning with the day of the award of the second framework in the scheme;

(b)for the expiry of one framework on the award of the next (but see subsection (3));

(c)for the final framework to expire at the end of the period of eight years beginning with the day on which the first framework under the scheme is awarded.

(3)An open framework may provide that, if a framework expires in accordance with subsection (2)(b) while a process for the award of a contract in accordance with the framework is ongoing, the contracting authority may continue the process and award the contract as though the framework had not expired.

(4)If there is no limit on the number of suppliers that can be party to a framework under an open framework, a contracting authority may award the framework to an existing supplier by reference to—

(a)the fact that the supplier has already been awarded a framework under the scheme,

(b)a tender relating to an earlier award under the scheme, or

(c)a tender relating to the current award.

(5)Otherwise, a contracting authority may award a framework under an open framework to an existing supplier by reference to—

(a)a tender relating to an earlier award of a framework under the scheme, or

(b)a tender relating to the current award.

(6)If a framework under an open framework is awarded to only one supplier, the framework, and the open framework, must expire before the end of the period of four years beginning with the day on which the framework is awarded.

(7)Subsection (6) applies despite subsection (2)(c) and any term of the framework or open framework.

(8)In this section, an “existing supplier” means a supplier that is party to a framework under the open framework.

(9)A reference to an award on substantially the same terms is a reference to an award that could be made by reference to the same tender or transparency notice without substantial modification (see section 31).

(10)A framework under an open framework may not be awarded under section 41 (direct award in special cases) or 43 (switching to direct award).

Commencement Information

I5S. 49 not in force at Royal Assent, see s. 127(2)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources