51Standstill periods on the award of contractsU.K.

This section has no associated Explanatory Notes

(1)A contracting authority may not enter into a public contract before—

(a)the end of the mandatory standstill period, or

(b)if later, the end of another standstill period provided for in the contract award notice.

(2)The “mandatory standstill period” is the period of eight working days beginning with the day on which a contract award notice is published in respect of the contract.

(3)Subsection (1) does not apply in relation to a contract that is—

(a)awarded under section 41 by reference to paragraph 13 of Schedule 5 (direct award: extreme and unavoidable urgency);

(b)awarded under section 41 by reference to regulations under section 42 (direct award to protect life, etc);

(c)awarded under section 41 or 43 (direct award and switching to direct award) by a private utility;

(d)awarded in accordance with a framework;

(e)awarded by reference to a dynamic market;

(f)a light touch contract.

(4)If a contract is of a kind described in subsection (3), a contracting authority may not enter into the contract before the end of any standstill period (a “voluntary standstill period”) provided for in the contract award notice.

(5)A voluntary standstill period may not be less than a period of eight working days beginning with the day on which the contract award notice is published.

Modifications etc. (not altering text)

Commencement Information

I1S. 51 not in force at Royal Assent, see s. 127(2)

I2S. 51 in force at 24.2.2025 by S.I. 2024/716, Sch. (as amended by S.I. 2024/959, regs. 1(2), 2(7)(a))

Back to top

Options/Help

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?