xmlns:atom="http://www.w3.org/2005/Atom"

PART 8Information and notices: general provision

93Pipeline notices

(1)This section applies in relation to any contracting authority that considers that, in the coming financial year, it will pay more than £100 million under relevant contracts.

(2)A contracting authority must publish a pipeline notice before the end of the period of 56 days beginning with the first day of the financial year referred to in subsection (1).

(3)A “pipeline notice” means a notice setting out specified information about any public contract with an estimated value of more than £2 million in respect of which the contracting authority intends to publish a tender notice or transparency notice during the reporting period.

(4)In this section—

(5)A Minister of the Crown or the Welsh Ministers may by regulations amend this section for the purpose of changing the financial thresholds.

(6)This section does not apply to—

(a)private utilities, or

(b)a transferred Northern Ireland authority.