Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Chapter
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 60


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 31/03/2024.
Changes to legislation:
There are currently no known outstanding effects for the Levelling-up and Regeneration Act 2023, Section 60.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
60Changes to mayoral combined authority’s area: additional requirementsE+W
This section has no associated Explanatory Notes
(1)An order under section 106 of the Local Democracy, Economic Development and Construction Act 2009 which adds a local government area to an existing area of a mayoral combined authority may only be made during the relevant period if the consultation requirements in subsection (2) are met.
(2)The consultation requirements are as follows—
(a)the Secretary of State has consulted the Local Government Boundary Commission for England,
(b)the mayor for the area of the combined authority has consulted the residents of the local government area which is to be added to that area, and
(c)the mayor has given the Secretary of State a report providing information about the consultation carried out under paragraph (b), and the Secretary of State has laid the report before Parliament.
(3)In this section, “the relevant period” means the period of 9 months beginning with the day on which this Act is passed.