SCHEDULES

FIRST SCHEDULEE+W+S Applications for Grant of Pipe-line Construction and Diversion Authorisations

Modifications etc. (not altering text)

C1Sch. 1: transfer of certain functions (1.7.1999) by S.I. 1999/1750, arts. 1, 2, Sch. 1 (with art. 7)

Sch. 1: certain functions exercisable (30.6.1999) by S.I. 1999/1756, arts. 1, 2, Sch. para. 1 (with art. 8)

Part IE+W+S Applications for Grant of Pipe-line Construction Authorisations

1E+W+SAn application for the grant of a pipe-line construction authorisation must be made to the Minister in writing and must—

(a)state the name and address of the person who will be the owner of the proposed pipe-line;

(b)specify the points between which the proposed pipe-line is to run and be accompanied by three copies of a map (whereof the scale shall be not less than that of [F11 in 10,560]) on which is delineated the route between those points which, subject to lateral deviation therefrom within such limits (if any) as may be specified in the authorisation, it is to take;

(c)state whether or not the grant of any rights or the giving of any street or river works consents is requisite to enable the proposed pipe-line to be constructed and to be, during the period during which it may reasonably be expected to remain, inspected, maintained, adjusted, repaired and renewed and, if it be the case that the grant of any rights or the giving of any such consents is requisite for that purpose, specify the rights and consents the grant or giving of which is so requisite and state, with respect to each of them, whether the grant or giving thereof has been, or can be, obtained;

(d)state what is proposed to be conveyed in the proposed pipe-line;

(e)contain such other (if any) particulars as may be prescribed.

Textual Amendments

F1Words in Sch. 1 para. 1(b) substituted (1.1.1995) by S.I. 1992/449, reg. 2(2)(a)(ii)