- Latest available (Revised)
- Point in Time (22/09/2017)
- Original (As enacted)
Version Superseded: 31/01/2024
Point in time view as at 22/09/2017. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are outstanding changes not yet made by the legislation.gov.uk editorial team to Land Compensation Act 1961. Any changes that have already been made by the team appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)This section has effect for the purposes of section 6D(3).
(2)The scheme referred to in that section includes the relevant transport project only if—
(a)regeneration or redevelopment was part of the published justification for the relevant transport project,
(b)the works comprised in the relevant transport project are first opened for use after the period of 5 years beginning with 22nd September 2017,
(c)the instrument authorising the compulsory acquisition of the land which is acquired for regeneration or redevelopment was made or prepared in draft on or after 22nd September 2017,
(d)the compulsory acquisition of that land is authorised before the end of the period of 5 years beginning with the day on which the works comprised in the relevant transport project are first opened for use, and
(e)that land is in the vicinity of land comprised in the relevant transport project.
(3)In assessing compensation payable to a person in respect of the compulsory acquisition of that land, the scheme is to be treated as if it did not include the relevant transport project if the person acquired the land—
(a)after plans for the relevant transport project were announced, but
(b)before 8 September 2016.
(4)Subsections (5) and (6) set out how subsection (2)(b) should be applied if a claim for compensation is made by a person (the “claimant”)—
(a)during the period of 5 years mentioned in that subsection, and
(b)before the works are first opened for use.
(5)Compensation is to be assessed on the basis that the works will first be opened for use after the period of 5 years unless the acquiring authority confirms that, in the authority's opinion, the works will first be opened during that period (in which case compensation is to be assessed on the basis that the works will first be opened for use during that period).
(6)If the basis on which compensation was assessed proves to be incorrect—
(a)the claimant's entitlement to any compensation which the claimant has already been awarded is not affected,
(b)the acquiring authority must give the claimant a notice informing the claimant that the basis on which the compensation was assessed was incorrect,
(c)the claimant may make a further claim for compensation in respect of the compulsory acquisition, and
(d)for the purposes of the Limitation Act 1980, the further claim for compensation accrues on the day the claimant receives the notice.]
Textual Amendments
F1Ss. 6A-6E substituted for ss. 6-9 (22.9.2017) by Neighbourhood Planning Act 2017 (c. 20), ss. 32(3), 46(1); S.I. 2017/936, reg. 3(b) (with reg. 4 and regs. 6, 7 which amend the new s. 6E(2)(b)(c))
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: