xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"
Modifications etc. (not altering text)
C1Pt. I (ss. 1-33) saved (25.7.1991) by Highland Regional Council (Harbours) Order Confirmation Act 1991 (c. xii), s. 1, Sch., s. 61(1)(e)
(1)Subject to the provisions of the next following subsection, where a works scheme prepared by an authority is confirmed by the Minister the authority shall have power to take all necessary steps for carrying out the work provided for by the scheme.
(2)Where a works scheme specifies work to be carried out on land neither vested in the authority nor proposed to be acquired by them for the purposes of the scheme, the owner of the land may, at any time not later than the expiration of six weeks after the confirmation of the scheme, serve a notice on the authority stating that he proposes to carry out the work; and where such a notice is served and not withdrawn, the authority shall not, except in accordance with the next following subsection, carry out that work.
(3)Where an owner by whom a notice has been served under the last foregoing subsection fails to carry out the work to which the notice relates in accordance with the scheme, the authority may give notice to him that unless the work is so carried out within such period as may be specified in the notice the authority will themselves carry out the work; and if where such a notice has been given by the authority the work is not so carried out within the said period, the authority shall have power to take all necessary steps for carrying out the work in accordance with the scheme.
(4)Section five of this Act shall not apply to any proposal of a coast protection authority to carry out work provided for by a works scheme.