Precautions after use of apparatus for cutting, welding or heating metal

58.—(1) In the case of apparatus on board a vessel and used for cutting, welding or heating metal with the aid of oxygen or any inflammable gas or vapour supplied under pressure, the precautions specified in the following paragraphs of this Regulation shall be taken when such use ceases for the day or for a substantial period and the apparatus is to be left on board, but need not be taken when such use is discontinued merely during short interruptions of work. The requirements in paragraphs (3) and (4) of this Regulation shall not apply during a meal interval.

(2) Supply valves of cylinders, generators and gas mains shall be securely closed.

(3) Movable pipes or hoses used for conveying oxygen or inflammable gas or vapour shall, in the case of a vessel undergoing construction, be brought to the topmost completed deck or, in the case of a vessel undergoing repair, to a weather deck or in either case to some other place of safety which is adequately ventilated to prevent any dangerous concentration of gas or fumes:

Provided that where, owing to the nature of the work, it is impracticable to comply with the foregoing requirements of this paragraph, the pipes or hoses shall be disconnected from cylinders, generators or gas mains, as the case may be.

(4) When cylinders or acetylene generating plant have been taken below deck as permitted by paragraph (2) of Regulation 55, such cylinders or acetylene generating plant shall be brought to a weather deck or, in the case of a vessel undergoing construction, to the topmost completed deck.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources