2.  In this Order —

“the Act” means the Petroleum and Submarine Pipe-lines Act 1975;

“Thistle A” means the offshore installation known as the Thistle A Platform which is situated above the Thistle oilfield, north-east of the Shetland Islands;

“Dunlin A” means the offshore installation known as the Dunlin A Platform which is situated above the Dunlin oilfield, north-east of the Shetland Islands;

“Cormorant A” means the offshore installation known as the Cormorant A Platform which is situated above the South Cormorant oilfield, north-east of the Shetland Islands;

“the Thistle SALM” means the single anchor leg mooring which is situated above the Thistle oilfield, north-east of the Shetland Islands;

“the Thistle to Dunlin pipe-line” means the 16 inch nominal diameter pipe brought into use on the 5th December 1978, which lies between Thistle A and Dunlin A and the apparatus and works associated therewith;

“the Thistle to Thistle SALM pipe-line” means the two 16 inch nominal diameter pipes brought into use on the 11th Feburary 1978, which lie between Thistle A and the Thistle SALM and the apparatus and works associated therewith;

“the riser” means that section of the Thistle to Dunlin pipe-line which connects Dunlin A to that section of the pipe-line which lies in, or in close proximity to, the sea-bed and which extends outwards from Dunlin A;

“the platform apparatus” means apparatus and works of a kind specified in paragraph (a), (aa), (b), (c), (d), (e) or (f) of section 33(1) of the Act(1)which is part of the Thistle to Dunlin pipe-line and is attached to Dunlin A;

“the bypass pipe-line” means the 16 nominal diameter pipe, together with the apparatus and works associated therewith, brought into use on the 5th December 1978, which lies between the Thistle to Dunlin pipe-line and the pipe-line which extends between Dunlin A and Cormorant A.

(1)

Section 33(1) was amended by the Oil and Gas (Enterprise) Act 1982 (c. 23), section 25(1).