Requirement to make arrangements etc
3. Each public electricity supplier in England and Wales (whose names are specified in column 1 of Schedule 1 (specified aggregate amounts of non-fossil fuel generating capacity) to this Order) shall, before 1st April 1990, make (in so far as he has not already done so) and produce to the Director evidence showing that he has made such arrangements as will secure that, subject to article 4 of this Order, for each period listed against the name of the supplier in column 2 of that Schedule, the aggregate amount of non-fossil fuel generating capacity available to him from relevant non-fossil fuel generating stations will not be less than that specified in column 3 of the Schedule in relation to that period.