Prescribed extent: single contracts4

1

This regulation applies where there is one contract only for the purchase of eligible electricity to be conveyed to the United Kingdom by means of a particular interconnector.

2

Where the contract capacity is equal to or less than the interconnector capacity, the whole of the contract capacity shall be treated for the purposes of section 32(5)(a) of the Act as generated by a non-fossil fuel generating station.

3

Where the contract capacity is greater than the interconnector capacity, only that part of the contract capacity which is equal to the interconnector capacity shall be treated for the purposes of section 32(5)(a) of the Act as generated by a non-fossil fuel generating station.